5016 1/2 N WILKINSON AVE 91607

Certificate Information: 5016 1/2 N WILKINSON AVE 91607

Application / Permit
21014-30000-01471
Plan Check / Job No.
B21WL01306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
garage conversion to ADU and new 2nd story addition
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 TARIK SAOUD
Corrections Issued 4/6/2021 TARIK SAOUD
Quality Review Completed 4/14/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/24/2021 TARIK SAOUD
Plan Check Approved 8/24/2021 TARIK SAOUD
Issued 9/8/2021 APPLICANT
CofO in Progress 7/1/2022 RAFAEL CORTES
CofO in Progress 8/4/2022 RAFAEL CORTES
Permit Finaled 8/5/2022 RONALD MYRICK
CofO Issued 8/5/2022 RONALD MYRICK
Permit Finaled 8/5/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/20/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/21/2021 JOHN TRIANTAFYLLOS
Specific Plan Cleared 4/21/2021 ERIN NASH
Eng Process Fee Ord 176,300 Cleared 5/14/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 5/28/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/10/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/16/2021 GABRIEL ROBLES

Contact Information

Contractor Mandoyan Construction Inc; Lic. No.: 559528-B 18034 VENTURA BLVD #287      ENCINO, CA 91316
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/29/2021 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/15/2021 Approved CHRISTOPHE COCHRAN
Sewer 10/20/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 10/27/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 10/27/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 11/15/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/3/2021 Partial Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/3/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 12/3/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/3/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/9/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/9/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/9/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 12/13/2021 Approved ASHLEY THOMPSON
Drywall Nailing 12/17/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 12/28/2021 Approved CHRISTOPHE COCHRAN
Gas Test 2/1/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 2/28/2022 Approved CHRISTOPHE COCHRAN
HVAC-Final 2/28/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Final 6/30/2022 OK to Issue CofO RAFAEL CORTES
Green Building Final 6/30/2022 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 6/30/2022 Approved RAFAEL CORTES
Final 8/4/2022 OK to Issue CofO RAFAEL CORTES
Service/Power Release 8/4/2022 Approved RAFAEL CORTES