5016 1/2 N WILKINSON AVE 91607
Certificate Information: 5016 1/2 N WILKINSON AVE 91607
- Application / Permit
- 21014-30000-01471
- Plan Check / Job No.
- B21WL01306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- garage conversion to ADU and new 2nd story addition
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TARIK SAOUD |
| Corrections Issued | 4/6/2021 | TARIK SAOUD |
| Quality Review Completed | 4/14/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/24/2021 | TARIK SAOUD |
| Plan Check Approved | 8/24/2021 | TARIK SAOUD |
| Issued | 9/8/2021 | APPLICANT |
| CofO in Progress | 7/1/2022 | RAFAEL CORTES |
| CofO in Progress | 8/4/2022 | RAFAEL CORTES |
| Permit Finaled | 8/5/2022 | RONALD MYRICK |
| CofO Issued | 8/5/2022 | RONALD MYRICK |
| Permit Finaled | 8/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/21/2021 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 4/21/2021 | ERIN NASH |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 5/28/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/10/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Mandoyan Construction Inc; Lic. No.: 559528-B | 18034 VENTURA BLVD #287 ENCINO, CA 91316 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/20/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/27/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 11/15/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/3/2021 | Partial Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/3/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/3/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/3/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/9/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/9/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/13/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 12/17/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/28/2021 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 2/1/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/28/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 2/28/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 2/28/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 6/30/2022 | OK to Issue CofO | RAFAEL CORTES |
| Green Building Final | 6/30/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 6/30/2022 | Approved | RAFAEL CORTES |
| Final | 8/4/2022 | OK to Issue CofO | RAFAEL CORTES |
| Service/Power Release | 8/4/2022 | Approved | RAFAEL CORTES |