1761 S BEDFORD ST 90035

Certificate Information: 1761 S BEDFORD ST 90035

Application / Permit
21014-30000-01439
Plan Check / Job No.
B21WL01294
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of (E) detached garage to ADU (Per Ordinance)
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 HOOMAN HAJIZADEH
Corrections Issued 4/15/2021 HOOMAN HAJIZADEH
Quality Review Completed 4/23/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/7/2022 HOOMAN HAJIZADEH
Plan Check Approved 2/25/2022 HOOMAN HAJIZADEH
Building Plans Picked Up 2/28/2022 APPLICANT
Issued 6/29/2022 APPLICANT
CofO in Progress 3/1/2023 JEREMY TODD
Permit Finaled 3/10/2023 DANIEL ORRANTE
CofO Issued 3/10/2023 DANIEL ORRANTE
Permit Finaled 3/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/3/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/1/2021 RENZ SORIANO
Sewer availability Cleared 7/1/2021 RENZ SORIANO
Low Impact Development Cleared 8/31/2021 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/17/2021 CELINA MORENO

Contact Information

Contractor Shupex Co; Lic. No.: 1059422-B 70 DAPPLEGRAY RD      BELL CANYON, CA 91307
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406
Engineer Yadegari,, Shahriar; Lic. No.: C64591 10301 KESWICK AVE      LOS ANGELES, CA 90064
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2022 Corrections Issued EVAN COOPER
Sewer 7/5/2022 Approved EVAN COOPER
Deputy Drilled-In Anchors 7/11/2022 Approved EVAN COOPER
Footing/Foundation/Slab 7/11/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 7/11/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 7/11/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 7/11/2022 Approved EVAN COOPER
Pre-Inspection 7/12/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 8/17/2022 Approved EVAN COOPER
Wood Frame 8/17/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 8/25/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 8/30/2022 Partial Approval EVAN COOPER
Shower Pan 8/30/2022 Approved EVAN COOPER
Interior/Exterior Lathing 9/1/2022 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 9/7/2022 Approved EVAN COOPER
Green Building Rough 9/7/2022 Approved EVAN COOPER
HVAC-Rough 9/7/2022 Approved EVAN COOPER
Interior/Exterior Lathing 9/7/2022 Partial Approval EVAN COOPER
METHANE-Rough 9/7/2022 Approved EVAN COOPER
Insulation 9/12/2022 Corrections Issued ANDREW NAVE
Drywall Nailing 9/21/2022 Approved EVAN COOPER
Insulation 9/21/2022 Approved EVAN COOPER
Interior/Exterior Lathing 10/3/2022 Approved EVAN COOPER
Special/Order Compliance 10/3/2022 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 10/6/2022 Approved EVAN COOPER
ELECTRICAL-Final 12/16/2022 Corrections Issued JEREMY TODD
ELECTRICAL-Final 12/22/2022 Approved JEREMY TODD
HVAC-Final 12/22/2022 Not Ready for Inspection JEREMY TODD
PLUMBING-Final 1/24/2023 Approved JEREMY TODD
ELECTRICAL-Final 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 2/9/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/9/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 2/16/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Final 2/16/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 2/22/2023 Conditional Approval JEREMY TODD
Pre-Inspection 2/22/2023 Conditional Approval JEREMY TODD
HVAC-Final 2/27/2023 Approved JEREMY TODD
Final 2/28/2023 OK to Issue CofO JEREMY TODD