12036 W HAVELOCK AVE 90230
Certificate Information: 12036 W HAVELOCK AVE 90230
- Application / Permit
- 21014-30000-01386
- Plan Check / Job No.
- B21WL01261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Enclose existing front covered porch, interior remodel of existing single family dwelling with new uncovered front porch
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- Issued on 6/29/2021
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | MARJAN SHENASI |
| Corrections Issued | 3/25/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/11/2021 | MARJAN SHENASI |
| Plan Check Approved | 5/20/2021 | MARJAN SHENASI |
| Issued | 6/29/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/18/2021 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 10/18/2021 | Corrections Issued | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 10/20/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/3/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 12/8/2021 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 12/8/2021 | Approved | JOHN KAYON |
| Drywall Nailing | 12/13/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/13/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/16/2022 | Corrections Issued | PATRICK QUALEY |
| Final | 3/16/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Final | 3/16/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Final | 3/16/2022 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | PATRICK QUALEY |
| Smoke Detectors | 3/16/2022 | Approved | PATRICK QUALEY |
| Final | 4/21/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 4/21/2022 | Approved | PATRICK QUALEY |
| Special/Order Compliance | 5/12/2022 | Not Ready for Inspection | CLAYTON GRAHAM |