481 N BUNDY DR 90049

Certificate Information: 481 N BUNDY DR 90049

Application / Permit
21014-30000-01315
Plan Check / Job No.
B21WL01197
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
first floor, ground floor addition to existing 2-story SFD with attached garage
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 TARIK SAOUD
Corrections Issued 4/7/2021 TARIK SAOUD
Quality Review Completed 4/14/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/15/2021 TARIK SAOUD
Applicant returned to address corrections 7/6/2021 TARIK SAOUD
Applicant returned to address corrections 10/14/2021 TARIK SAOUD
Plan Check Approved 10/14/2021 TARIK SAOUD
Plan Check Approved 10/15/2021 TARIK SAOUD
Issued 10/21/2021 APPLICANT
Building Plans Picked Up 2/24/2022 APPLICANT
CofO in Progress 7/11/2022 CARLOS MATAMOROS
CofO in Progress 7/11/2022 JOHN KIDWELL
Permit Finaled 7/18/2022 DANIEL ORRANTE
CofO Issued 7/18/2022 DANIEL ORRANTE
Permit Finaled 7/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/28/2021 TRACY TATE
Low Impact Development Cleared 10/4/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/6/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 10/14/2021 TARIK SAOUD

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Ardsley Construction Co; Lic. No.: 248586-B 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 10/22/2021 Partial Approval CARLOS MATAMOROS
Drywall Nailing 10/27/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 10/28/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 10/29/2021 Conditional Approval CARLOS MATAMOROS
Drywall Nailing 11/2/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/5/2021 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 11/8/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/9/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/22/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 11/22/2021 Not Ready for Inspection JUAN VALENZUELA
Deputy Reinf. Concrete 11/23/2021 Conditional Approval MICHAEL PELHAM
Insulation 12/2/2021 Partial Inspection KRISTEN CAUSEY
Insulation 12/7/2021 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 12/7/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/7/2021 Partial Approval CARLOS MATAMOROS
Shower Pan 12/7/2021 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 12/10/2021 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 1/7/2022 Corrections Issued CARLOS MATAMOROS
Green Building Rough 1/7/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 1/13/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 1/13/2022 Approved CARLOS MATAMOROS
Insulation 1/13/2022 Approved CARLOS MATAMOROS
Insulation 1/13/2022 Partial Approval CARLOS MATAMOROS
Underground Mechanical 1/19/2022 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 1/20/2022 Approved CARLOS MATAMOROS
Underground Mechanical 1/20/2022 Approved CARLOS MATAMOROS
Underground Mechanical 1/24/2022 Approved CARLOS MATAMOROS
Insulation 3/30/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 5/25/2022 Corrections Issued CARLOS MATAMOROS
HVAC-Final 5/25/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/25/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 6/24/2022 Approved CARLOS MATAMOROS
Gas Test 6/24/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 6/24/2022 Approved CARLOS MATAMOROS
Final 7/1/2022 OK to Issue CofO JOHN KIDWELL
Footing/Foundation/Slab 7/1/2022 Approved JOHN KIDWELL
Green Building Final 7/1/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 7/1/2022 Approved JOHN KIDWELL
Final 7/11/2022 OK to Issue CofO CARLOS MATAMOROS