1072 S STEARNS DR 90035
Certificate Information: 1072 S STEARNS DR 90035
- Application / Permit
- 21014-30000-01295
- Plan Check / Job No.
- B21WL01166
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Additon and remodel (E) SFD.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | ALFREDO JARA |
| Corrections Issued | 3/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 4/23/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 5/26/2021 | KHUONG TRUONG |
| Plan Check Approved | 6/10/2021 | KHUONG TRUONG |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 12/15/2022 | JOSE AVILA |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/5/2021 | TERRI OSBORNE |
| ZI | Cleared | 4/5/2021 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | DINAH GARIN |
| HPOZ | Cleared | 5/18/2021 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 5/18/2021 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 5/18/2021 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ananian,, Vatche; Lic. No.: C79073 | 19528 VENTURA BLVD #374 TARZANA, CA 91356 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 7/23/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 7/23/2021 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 12/14/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/14/2022 | Approved | JOSE AVILA |
| Final | 12/14/2022 | OK to Issue CofO | JOSE AVILA |
| Footing/Foundation/Slab | 12/14/2022 | Approved | JOSE AVILA |
| Green Building Final | 12/14/2022 | Approved | JOSE AVILA |
| Green Building Rough | 12/14/2022 | Approved | JOSE AVILA |
| METHANE-Final | 12/14/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 12/14/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/14/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/14/2022 | Approved | JOSE AVILA |