520 N MANSFIELD AVE 90036
Certificate Information: 520 N MANSFIELD AVE 90036
- Application / Permit
- 21014-30000-01288
- Plan Check / Job No.
- B21WL01157
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of On-Grade Covered Patio to the Rear of (E) 1-Story S.F.D., remove and replace roof over patio on the side of the SFD.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/6/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/7/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/26/2022 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 8/29/2022 | JAHANSHAH POURHASSAN |
| Issued | 9/7/2022 | APPLICANT |
| Building Plans Picked Up | 9/7/2022 | APPLICANT |
| CofO in Progress | 8/5/2024 | BRIAN SULLIVAN |
| Permit Finaled | 1/16/2025 | DEROLD HAUFF |
| CofO Issued | 1/16/2025 | DEROLD HAUFF |
| Permit Finaled | 1/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | CINDY QI |
| Low Impact Development | Cleared | 5/11/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yates,, Gerald Lee; Lic. No.: C73972 | 6309 DEL AMO BLVD LAKEWOOD, CA 90713 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| METHANE-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Final | 1/31/2024 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Green Building Final | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 1/31/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Final | 8/2/2024 | OK to Issue CofO | BRIAN SULLIVAN |