3641 S ROSEWOOD AVE 90066
Certificate Information: 3641 S ROSEWOOD AVE 90066
- Application / Permit
- 21014-30000-01287
- Plan Check / Job No.
- B21WL01155
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) S.F.D., Interior Remodel, and (N) Covered Porch
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | RICHARD GARCIA |
| Corrections Issued | 3/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 4/15/2021 | DAVID CASTILLO |
| Issued | 4/27/2021 | APPLICANT |
| CofO in Progress | 3/1/2022 | ENRIQUE MIRELES |
| CofO in Progress | 3/1/2022 | ENRIQUE MIRELES |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
| CofO Issued | 3/8/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/30/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 4/1/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 4/7/2021 | KIRK LINKLATER |
| Specific Plan | Cleared | 4/8/2021 | FREDDY GARCIA |
Contact Information
| Contractor | Capaway Construction; Lic. No.: 884072-B | 23715 ARCHWOOD STREET WEST HILLS, CA 91307 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 5/3/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/4/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/17/2021 | Partial Approval | PIERRE VEGA |
| Green Building Rough | 5/17/2021 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 5/17/2021 | Partial Approval | PIERRE VEGA |
| Underground Mechanical | 5/17/2021 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/10/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/10/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 6/28/2021 | Conditional Approval | RICHARD ROBLES |
| ELECTRICAL-Rough | 6/29/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/29/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/29/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 7/15/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/26/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/26/2021 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/26/2021 | Approved | JESUS RODRIGUEZ |
| Final | 12/1/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/1/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/1/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/1/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/1/2022 | OK to Issue CofO | ENRIQUE MIRELES |