930 N WESTERN AVE 1- 11 90029

Certificate Information: 930 N WESTERN AVE 1- 11 90029

Application / Permit
21014-30000-01260
Plan Check / Job No.
B21WL01140
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(35) Condo-Multi Family
Work Description
Enclose high ceiling area in retail portion and add to 2nd floor (1,932 sf) ; Propose 3 office spaces at new 2nd floor space ; Change of use at 1 st floor from one retail space (5,204 sf) to 8 office spaces
Permit Issued
Issued on 2/14/2023
Issuing Office
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 TARIK SAOUD
Corrections Issued 3/23/2021 TARIK SAOUD
Quality Review Completed 3/31/2021 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 4/30/2021 APPLICANT
Green Plans Picked Up 12/22/2021 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
Plan Check Approved 2/13/2023 REZA HAGHIGHAT
Issued 2/14/2023 APPLICANT
CofO in Progress 6/3/2026 LUIS CCAMACHO
Permit Finaled 6/3/2026 RAFAEL ESPINOZA
CofO Issued 6/3/2026 RAFAEL ESPINOZA
Permit Finaled 6/3/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

ZA Case Cleared 5/4/2021 JOE LUCKEY
ZA Case Cleared 5/4/2021 JOE LUCKEY
"Q" conditions Cleared 8/18/2021 JOE LUCKEY
Miscellaneous Cleared 8/18/2021 JOE LUCKEY
Miscellaneous Cleared 8/18/2021 JOE LUCKEY
Tract Map conditions Cleared 8/18/2021 JOE LUCKEY
CPC Cleared 8/20/2021 JOE LUCKEY
Green Code Cleared 1/6/2022 RICHARD GARCIA
Fire Marshal Fire Life Safety Cleared 11/2/2022 VIDAL GARCIA
Eng Process Fee Ord 176,300 Cleared 11/30/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 11/30/2022 CHRISTOPHER ROCHA
Address approval Cleared 12/1/2022 CHRISTOPHER ROCHA
Highway dedication Cleared 12/1/2022 CHRISTOPHER ROCHA
DAS Clearance Cleared 12/28/2022 TARIK SAOUD

Contact Information

Architect Uriu,, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Owner-Builder       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2023 Partial Approval MARTIN TAVITIAN
Structural Steel Frame 11/29/2023 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 12/14/2023 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 1/3/2024 Partial Approval MARTIN TAVITIAN
Footing/Foundation/Slab 1/25/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 3/7/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 3/19/2024 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 3/28/2024 Partial Inspection TIMOTHY POWELL
Interior/Exterior Lathing 7/12/2024 Approved TIMOTHY POWELL
Light Gage Steel Frame 8/2/2024 Partial Inspection TIMOTHY POWELL
Light Gage Steel Frame 10/9/2024 Not Ready for Inspection LUIS CCAMACHO
Insulation 10/16/2024 Not Ready for Inspection LUIS CCAMACHO
Light Gage Steel Frame 10/16/2024 Partial Approval LUIS CCAMACHO
Insulation 10/21/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 11/8/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 11/14/2024 Not Ready for Inspection LUIS CCAMACHO
Interior/Exterior Lathing 12/4/2024 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 12/4/2024 Partial Approval TIMOTHY POWELL
Masonry Wall/Backfill 12/10/2024 Partial Inspection TIMOTHY POWELL
Drywall Nailing 12/26/2024 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 1/14/2025 Partial Approval TIMOTHY POWELL
Final 1/26/2026 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 1/26/2026 Approved LUIS CCAMACHO
Green Building Final 1/26/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Rough 1/26/2026 Approved LUIS CCAMACHO
Reinforced Concrete Frame 1/26/2026 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 1/26/2026 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 1/26/2026 Approved LUIS CCAMACHO
Final 2/3/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 2/3/2026 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 2/3/2026 Not Ready for Inspection LUIS CCAMACHO
Final 3/2/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 3/2/2026 Not Ready for Inspection LUIS CCAMACHO
Smoke Detectors 3/2/2026 Not Ready for Inspection LUIS CCAMACHO
Pre-Inspection 3/13/2026 Partial Inspection LUIS CCAMACHO
Final 5/21/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 5/21/2026 Approved LUIS CCAMACHO
Smoke Detectors 5/21/2026 Approved LUIS CCAMACHO
Final 5/28/2026 Partial Inspection LUIS CCAMACHO
Final 6/2/2026 OK to Issue CofO LUIS CCAMACHO