7706 S BELAND AVE 90045
Certificate Information: 7706 S BELAND AVE 90045
- Application / Permit
- 21014-30000-01227
- Plan Check / Job No.
- B21WL01119
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (417 sf) to rear side and remodel of (e) single story SFD w./ att. garage to add a master bedroom and a master bathroom.
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | MANUEL GARCIA |
| Corrections Issued | 3/23/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 5/20/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 7/19/2021 | KHUONG TRUONG |
| Plan Check Approved | 8/6/2021 | JAHANSHAH POURHASSAN |
| Issued | 8/10/2021 | APPLICANT |
| CofO in Progress | 4/21/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 4/21/2022 | DANIEL ORRANTE |
| CofO Issued | 4/21/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/21/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/5/2021 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 5/20/2021 | MANUEL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | DENNIS BRAGIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Hamodot Isaac; Lic. No.: 1071940-B | 7840 W 81 STREET PLAYA DEL REY, CA 90293 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2021 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 8/19/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 8/19/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Conditional Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 9/2/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/27/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/27/2021 | Approved | JOHNNY MIRANDA |
| Wood Frame | 9/27/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 10/8/2021 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 10/8/2021 | Corrections Issued | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/8/2021 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/29/2021 | Partial Approval | JOHN KAYON |
| Green Building Rough | 10/29/2021 | Partial Approval | JOHN KAYON |
| Insulation | 10/29/2021 | Partial Approval | JOHN KAYON |
| Interior/Exterior Lathing | 10/29/2021 | Partial Approval | JOHN KAYON |
| Rough-Elec/Plmb/HVAC | 10/29/2021 | Partial Approval | JOHN KAYON |
| Drywall Nailing | 11/8/2021 | Approved | DAVID FEILER |
| Green Building Rough | 11/8/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/29/2021 | Approved | JOHN KAYON |
| Shower Pan | 11/29/2021 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 1/19/2022 | Approved | DAVID FEILER |
| Final | 1/19/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 1/19/2022 | Approved | DAVID FEILER |
| Green Building Final | 1/19/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 1/19/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 2/3/2022 | Partial Approval | DAVID FEILER |
| Smoke Detectors | 2/3/2022 | Approved | DAVID FEILER |
| Final | 3/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/14/2022 | Approved | JESUS RODRIGUEZ |
| Final | 4/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 4/14/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/14/2022 | Approved | JESUS RODRIGUEZ |
| Final | 4/21/2022 | OK to Issue CofO | JESUS RODRIGUEZ |