382 N SALTAIR AVE 90049
Certificate Information: 382 N SALTAIR AVE 90049
- Application / Permit
- 21014-30000-01092
- Plan Check / Job No.
- B21WL01007
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (e) 1-story SFD Per engineering design.
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | ALFREDO JARA |
| Corrections Issued | 3/15/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/12/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/15/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/29/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/18/2021 | ALFREDO JARA |
| Plan Check Approved | 7/26/2021 | ALFREDO JARA |
| Issued | 7/26/2021 | APPLICANT |
| CofO in Progress | 7/21/2023 | CARLOS MATAMOROS |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/11/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 6/29/2021 | ALFREDO JARA |
Contact Information
| Contractor | D'Angelo Construction; Lic. No.: 406563-B | 11319 SHELDON STREET SUN VALLEY, CA 91352 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/23/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 10/1/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 10/4/2021 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/7/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 5/5/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/5/2022 | Approved | CARLOS MATAMOROS |
| Sewer | 5/5/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/19/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/2/2022 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/28/2022 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 6/28/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 6/30/2022 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/6/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/6/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/15/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/27/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 12/7/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/19/2023 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 5/10/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/29/2023 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 6/29/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 6/29/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 6/29/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/29/2023 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/29/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 7/5/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 7/5/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 7/5/2023 | Approved | CARLOS MATAMOROS |
| Final | 7/20/2023 | OK to Issue CofO | CARLOS MATAMOROS |