5915 W ABERNATHY DR 90045
Certificate Information: 5915 W ABERNATHY DR 90045
- Application / Permit
- 21014-30000-01077
- Plan Check / Job No.
- B21WL00991
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two-story S.F.D. w/ att. two-car garage
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Current Status
- CofO Issued on 2/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 5/4/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 5/11/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/24/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Applicant returned to address corrections | 1/26/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 5/3/2022 | FELIPE HERNANDEZ |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 2/3/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 2/3/2025 | RICHARD STEINBACH |
| CofO Issued | 2/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/7/2021 | BRIAN MILLER |
| Permit | Cleared | 10/5/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 10/8/2021 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 10/16/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 11/1/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 12/28/2021 | ADALBERTO VERA |
Contact Information
| Architect | Pratt,, Dean Lawrence; Lic. No.: C22055 | 113 1/2 N LA BREA AVENUE STE 114 LOS ANGELES, CA 90036 |
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | 1545 SAWTELLE BLVD STE 22 LOS ANGELES, CA 90025 |
| Engineer | Jung,, Jason; Lic. No.: C80569 | 106 S SIERRA MADRE BLVD UNIT #2 PASADENA, CA 91107 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2023 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 4/27/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 5/18/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 5/23/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 5/23/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/1/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 6/15/2023 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 6/15/2023 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 6/15/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | BOBBY KEY |
| Insulation | 6/29/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 12/14/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/29/2024 | Approved | BOBBY KEY |
| Green Building Rough | 1/29/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 1/29/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/29/2024 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 1/29/2024 | Approved | BOBBY KEY |
| Insulation | 2/23/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 2/29/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/11/2024 | Approved | BOBBY KEY |
| Shower Pan | 4/11/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/6/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 9/6/2024 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 9/19/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 9/19/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 9/19/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/20/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 10/8/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Final | 10/8/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 10/8/2024 | Partial Approval | BOBBY KEY |
| HVAC-Final | 10/15/2024 | Corrections Issued | BOBBY KEY |
| Final | 12/23/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/23/2024 | Approved | EVAN COOPER |
| HVAC-Final | 12/23/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/23/2024 | Approved | EVAN COOPER |
| Final | 1/31/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Service/Power Release | 1/31/2025 | Approved | TEMISTOCLES CAAL |