3637 S MOORE ST 90066
Certificate Information: 3637 S MOORE ST 90066
- Application / Permit
- 21014-30000-00986
- Plan Check / Job No.
- B21WL00918
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE TO ADU W/ NON-HABITABLE BASEMENT PER CA GOVT. CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Current Status
- CofO Issued on 7/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 4/9/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 4/16/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/20/2021 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/30/2022 | HOOMAN HAJIZADEH |
| Issued | 9/12/2022 | APPLICANT |
| Building Plans Picked Up | 9/15/2022 | APPLICANT |
| CofO in Progress | 7/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 7/16/2024 | DANIEL ORRANTE |
| CofO Issued | 7/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 8/11/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 8/12/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 12/17/2021 | ROBERT DUFF |
| Excavation more than 5-ft deep | Cleared | 2/18/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 2/18/2022 | HOOMAN HAJIZADEH |
Contact Information
| Contractor | Lonestar West Construction; Lic. No.: 768001-B | 3656 MC LAUGHLIN AVENUE LOS ANGELES, CA 90066 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/22/2022 | Partial Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/22/2022 | Partial Inspection | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 2/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 4/24/2023 | Partial Approval | JESUS RODRIGUEZ |
| Pre-Inspection | 4/24/2023 | Partial Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/19/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 7/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/19/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 8/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 8/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 8/3/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/8/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/21/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/21/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 8/25/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/30/2023 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 8/30/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/30/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/16/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/16/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 1/18/2024 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| Final | 5/16/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Not Required | JESUS RODRIGUEZ |
| Smoke Detectors | 5/16/2024 | Approved | JESUS RODRIGUEZ |
| Final | 6/26/2024 | Corrections Issued | MICHAEL PELHAM |
| Green Building Final | 6/26/2024 | Approved | MICHAEL PELHAM |
| Final | 7/9/2024 | OK to Issue CofO | JESUS RODRIGUEZ |