24532 W EILAT ST 91367
Certificate Information: 24532 W EILAT ST 91367
- Application / Permit
- 21014-30000-00934
- Plan Check / Job No.
- B21WL00883
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 4/16/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 4/16/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/26/2021 | SERGIO SILVA |
| Plan Check Approved | 9/1/2021 | SERGIO SILVA |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 10/18/2022 | TROY SANDERS |
| Permit Finaled | 10/24/2022 | JOHN JANSON |
| CofO Issued | 10/24/2022 | JOHN JANSON |
| Permit Finaled | 10/24/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/16/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2022 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Conditional Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/10/2022 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | TROY SANDERS |
| Green Building Rough | 8/24/2022 | Not Ready for Inspection | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 8/24/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 8/30/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/30/2022 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | TROY SANDERS |
| Final | 9/16/2022 | Corrections Issued | TROY SANDERS |
| Footing/Foundation/Slab | 9/16/2022 | Approved | TROY SANDERS |
| Green Building Final | 9/16/2022 | Approved | TROY SANDERS |
| Green Building Rough | 9/16/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/16/2022 | Approved | TROY SANDERS |
| Final | 10/17/2022 | OK to Issue CofO | TROY SANDERS |