8100 S BARNSLEY AVE 90045

Certificate Information: 8100 S BARNSLEY AVE 90045

Application / Permit
21014-30000-00920
Plan Check / Job No.
B21WL00872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and addition of a 9'-2 x 29'-3" covered front entry porch and 13'-2" x 22'-10" trellis to rear of the (E) SFD.
Permit Issued
Issued on 5/29/2022
Issuing Office
Current Status
Issued on 5/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 JAHANSHAH POURHASSAN
Corrections Issued 3/6/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/25/2021 MANUEL GARCIA
Applicant returned to address corrections 4/27/2021 RICHARD GARCIA
Applicant returned to address corrections 5/20/2021 MARJAN SHENASI
Applicant returned to address corrections 10/1/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 10/28/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/10/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/19/2021 JAHANSHAH POURHASSAN
Building Plans Picked Up 11/19/2021 APPLICANT
Plan Check Approved 12/2/2021 JAHANSHAH POURHASSAN
Issued 5/29/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/20/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 4/22/2021 DINAH GARIN
Low Impact Development Cleared 9/16/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/28/2021 DINAH GARIN

Contact Information

Architect Natvig,, Scott Andrew; Lic. No.: C31018 12528 GILMORE AVENUE      LOS ANGELES, CA 90066
Contractor Construction Services By Michael J Gatti Inc; Lic. No.: 847407-B 1009 OCCIDENTAL DRIVE      CLAREMONT, CA 91711
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/7/2022 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/24/2022 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 8/24/2022 Corrections Issued BOBBY KEY
Piling/Pier/Caisson 8/24/2022 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 2/8/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 9/18/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 9/18/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Corrections Issued BOBBY KEY
Deputy Wood Construction 9/20/2023 Conditional Approval BOBBY KEY
Deputy Wood Construction 9/27/2023 Conditional Approval BOBBY KEY
Deputy Wood Construction 9/28/2023 Conditional Approval RICHARD STEINBACH
Drywall Nailing 10/3/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 10/3/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 10/3/2023 Off-Hour Fees Due
ELECTRICAL-Rough 10/3/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Off-Hour Fees Due
Green Building Rough 10/3/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 10/3/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/3/2023 Corrections Issued HERBERT GIRON
Wood Frame 10/3/2023 Off-Hour Fees Due
ELECTRICAL-Rough 10/5/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 10/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 3/4/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 4/1/2024 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 4/15/2024 Partial Approval BOBBY KEY
Green Building Rough 4/15/2024 Approved BOBBY KEY
HVAC-Final 4/15/2024 Corrections Issued BOBBY KEY
HVAC-Rough 4/15/2024 Approved BOBBY KEY
Interior/Exterior Lathing 4/15/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 4/15/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 5/23/2024 No Access for Inspection BOBBY KEY
Insulation 5/23/2024 No Access for Inspection BOBBY KEY
BUILDING-Rough-Frame 5/28/2024 Approved BOBBY KEY
Insulation 5/28/2024 Approved BOBBY KEY
Drywall Nailing 10/1/2024 Approved BOBBY KEY
Service/Power Release 6/16/2025 Not Ready for Inspection TEMISTOCLES CAAL
Shower Pan 12/2/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 12/2/2025 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 2/26/2026 Corrections Issued JESUS PINEDA
Special/Order Compliance 2/26/2026 Corrections Issued JESUS PINEDA