10315 W GLENBARR AVE 90064
Certificate Information: 10315 W GLENBARR AVE 90064
- Application / Permit
- 21014-30000-00885
- Plan Check / Job No.
- B21WL00853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition at first floor of existing single family dwelling.
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2021 | MARJAN SHENASI |
| Corrections Issued | 3/2/2021 | MARJAN SHENASI |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Plan Check Approved | 4/6/2021 | KHUONG TRUONG |
| Issued | 5/27/2021 | APPLICANT |
| CofO in Progress | 12/23/2021 | KEVIN SARGSYAN |
| Permit Finaled | 12/27/2021 | KENNETH NAGLE |
| CofO Issued | 12/27/2021 | KENNETH NAGLE |
| Permit Finaled | 12/27/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/16/2021 | EILEEN HUNT |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 4/5/2021 | KIRK LINKLATER |
Contact Information
| Architect | Waingrow,, Diane Alexandra; Lic. No.: C22308 | 1014 MARONEY LANE PACIFIC PALISADES, CA 90272 |
| Contractor | Crane Steven & Co Inc; Lic. No.: 667129-B | 2959 SEPULVEDA BLVD LOS ANGELES, CA 90064 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 6/22/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 6/22/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/28/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/28/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/30/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 6/30/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 6/30/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/6/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 8/6/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 8/10/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/10/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 8/12/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | KEVIN SARGSYAN |
| Final | 11/5/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/5/2021 | Approved | KEVIN SARGSYAN |
| Green Building Final | 11/5/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/5/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 11/5/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 11/5/2021 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 11/5/2021 | Approved | KEVIN SARGSYAN |
| Final | 11/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 12/10/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 12/23/2021 | OK to Issue CofO | KEVIN SARGSYAN |