669 N EL MEDIO AVE 90272
Certificate Information: 669 N EL MEDIO AVE 90272
- Application / Permit
- 21014-30000-00882
- Plan Check / Job No.
- B21WL00850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) 2-Story S.F.D and New Deck with Trellis
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/21/2024
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | DAVID CASTILLO |
| Corrections Issued | 3/9/2021 | DAVID CASTILLO |
| Quality Review Completed | 3/19/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/12/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/29/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/13/2021 | DAVID CASTILLO |
| Plan Check Approved | 7/28/2021 | DAVID CASTILLO |
| Issued | 8/11/2022 | APPLICANT |
| Permit Finaled-Status Void | 6/7/2024 | EVAN COOPER |
| Permit Finaled | 6/7/2024 | EVAN COOPER |
| CofO in Progress | 7/30/2024 | EVAN COOPER |
| Re-Activate Permit | 9/21/2024 | EVAN COOPER |
| No Progress | 9/21/2024 | MICHAEL PELHAM |
| CofO in Progress | 9/21/2024 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | DINAH GARIN |
| Coastal Zone | Cleared | 6/29/2021 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 6/29/2021 | DAVID CASTILLO |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Root Enterprises Inc; Lic. No.: 872584-B | 17216 SATICOY ST #180 VAN NUYS, CA 91406 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/16/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 2/16/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 2/23/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 3/1/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 3/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Drywall Nailing | 3/7/2023 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 3/7/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/13/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/23/2023 | Partial Approval | BRENDAN LOONEY |
| Deck | 4/5/2023 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Approved | BRENDAN LOONEY |
| Wood Frame | 6/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 8/3/2023 | No Access for Inspection | KENNETH NAGLE |
| Pre-Inspection | 8/9/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/14/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/22/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 8/31/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 8/31/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/31/2023 | Approved | EVAN COOPER |
| Wood Frame | 8/31/2023 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 9/5/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/19/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 9/27/2023 | Approved | EVAN COOPER |
| Insulation | 9/27/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/28/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 10/12/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 10/12/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/19/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/30/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Final | 2/20/2024 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 3/7/2024 | Approved | EVAN COOPER |
| HVAC-Final | 3/7/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/10/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 6/7/2024 | Approved | EVAN COOPER |
| Final | 6/7/2024 | Permit Finaled | EVAN COOPER |
| Footing/Foundation/Slab | 6/7/2024 | Approved | EVAN COOPER |
| Green Building Final | 6/7/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/7/2024 | Approved | EVAN COOPER |