3003 N BEACHWOOD DR 90068
Certificate Information: 3003 N BEACHWOOD DR 90068
- Application / Permit
- 21014-30000-00837
- Plan Check / Job No.
- B21WL00816
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 218 SF GARAGE ATTIC CONVERSION TO ADU IN (E)DETCHED GARAGE. PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | ALFREDO JARA |
| Corrections Issued | 3/8/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/15/2021 | ALFREDO JARA |
| Plan Check Approved | 7/8/2021 | ALFREDO JARA |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 4/1/2024 | BRIAN SULLIVAN |
| Permit Finaled | 4/1/2024 | RONALD MYRICK |
| CofO Issued | 4/1/2024 | RONALD MYRICK |
| Permit Finaled | 4/1/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | JEANIE LAM |
| Miscellaneous | Cleared | 4/28/2021 | LIKYELESH ABERA |
| Hydrant and Access approval | Cleared | 5/11/2021 | MATTHEW CRAIG |
| Specific Plan | Cleared | 5/17/2021 | LIKYELESH ABERA |
| Grading Pre-Inspection | Cleared | 5/19/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Schevers Construction Llc; Lic. No.: 802078-B | 11177 LINDBLADE STREET CULVER CITY, CA 90230 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/1/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 2/1/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Rough-Elec/Plmb/HVAC | 2/1/2022 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 2/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/10/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 2/17/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 2/17/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 4/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Drywall Nailing | 4/11/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 4/11/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/6/2022 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/6/2022 | Approved | BRIAN SULLIVAN |
| Green Building Final | 6/6/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 6/6/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/6/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/14/2022 | Corrections Issued | HORACE FULTZ |
| Final | 4/1/2024 | OK to Issue CofO | BRIAN SULLIVAN |