241 S RUTH AVE 90291

Certificate Information: 241 S RUTH AVE 90291

Application / Permit
21014-30000-00830
Plan Check / Job No.
B21WL00811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-Story Addition (1,230 sf) to add a master bedroom, master bathroom, walking closet at 2nd floor, add a half bathroom and expand kitchen and living room at 1st floor; remodel (e) 1-Story SFD (2 bedrooms, 1 full bathroom) w./ att. porte cochère (1-car carport); add patio cover at 1st floor (132 sf), add balcony at 2nd floor (52 sf), add roof deck
Permit Issued
Issued on 11/11/2021
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 REZA HAGHIGHAT
Corrections Issued 3/30/2021 REZA HAGHIGHAT
Quality Review Completed 4/9/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 11/3/2021 REZA HAGHIGHAT
Issued 11/11/2021 APPLICANT
Building Plans Picked Up 12/14/2021 APPLICANT
CofO in Progress 2/17/2023 EVAN COOPER
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 5/19/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/1/2021 DINAH GARIN
Coastal Zone Cleared 9/28/2021 MAXFIELD VERMY
Specific Plan Cleared 9/28/2021 MAXFIELD VERMY
ZA Case Cleared 9/28/2021 MAXFIELD VERMY
ZA Case Cleared 9/28/2021 MAXFIELD VERMY
ZA Case Cleared 9/28/2021 MAXFIELD VERMY
ZA Case Cleared 9/28/2021 MAXFIELD VERMY
Low Impact Development Cleared 10/6/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/6/2021 DINAH GARIN

Contact Information

Contractor Butel Construction Inc; Lic. No.: 852273-B 257 SOUTH CITRUS AVE      LOS ANGELES, CA 90036
Engineer Galbreath,, Sean Martin; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/2/2022 Partial Approval DAVID FEILER
Footing/Foundation/Slab 2/17/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval DAVID FEILER
Deputy Wood Construction 5/27/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 8/8/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/8/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 8/8/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/16/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 8/16/2022 Approved DAVID FEILER
Final 8/16/2022 Corrections Issued DAVID FEILER
Green Building Rough 8/16/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 8/16/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/30/2022 Conditional Approval DAVID FEILER
Interior/Exterior Lathing 8/30/2022 Partial Approval DAVID FEILER
Shower Pan 8/30/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 9/9/2022 Approved DAVID FEILER
Green Building Rough 9/9/2022 Approved DAVID FEILER
HVAC-Rough 9/9/2022 Approved DAVID FEILER
Insulation 9/9/2022 Corrections Issued DAVID FEILER
Drywall Nailing 9/14/2022 Approved DAVID FEILER
Insulation 9/14/2022 Approved DAVID FEILER
Interior/Exterior Lathing 9/14/2022 Approved DAVID FEILER
Sewer 11/4/2022 Corrections Issued DAVID FEILER
Underground Mechanical 11/4/2022 Partial Approval DAVID FEILER
Sewer 11/28/2022 Approved DAVID FEILER
ELECTRICAL-Final 12/6/2022 Not Ready for Inspection EVAN COOPER
Final 12/6/2022 Not Ready for Inspection EVAN COOPER
Gas Test 12/6/2022 Not Ready for Inspection EVAN COOPER
Green Building Final 12/6/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 12/6/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 12/6/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 12/6/2022 Not Ready for Inspection EVAN COOPER
Smoke Detectors 12/6/2022 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 12/6/2022 Partial Inspection JEREMY TODD
Final 1/13/2023 Corrections Issued EVAN COOPER
Green Building Final 1/13/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready EVAN COOPER
Smoke Detectors 1/13/2023 Approved EVAN COOPER
Service/Power Release 1/18/2023 Approved EVAN COOPER
Gas Test 1/20/2023 Approved EVAN COOPER
ELECTRICAL-Final 2/17/2023 Approved EVAN COOPER
Final 2/17/2023 OK to Issue CofO EVAN COOPER
Green Building Final 2/17/2023 Approved EVAN COOPER
HVAC-Final 2/17/2023 Approved EVAN COOPER
PLUMBING-Final 2/17/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved EVAN COOPER