21147 S DALTON AVE 90501
Certificate Information: 21147 S DALTON AVE 90501
- Application / Permit
- 21014-30000-00812
- Plan Check / Job No.
- B21WL00794
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel to (E) 1-Story S.F.D
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 11/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | DAVID CASTILLO |
| Corrections Issued | 4/7/2021 | DAVID CASTILLO |
| Quality Review Completed | 4/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/18/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/5/2021 | DAVID CASTILLO |
| Plan Check Approved | 11/18/2021 | DAVID CASTILLO |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | EUGENE CASSIDY |
| CofO Issued | 11/3/2023 | ANSON MAGLASANG |
| Permit Finaled | 11/3/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/26/2021 | CHINH DINH |
| Grading Pre-Inspection | Cleared | 6/4/2021 | KIRK LINKLATER |
| Low Impact Development | Cleared | 10/27/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mokri-Arganeh,, Fattaneh; Lic. No.: C52608 | 2075 S COUNTRY CYN RD HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 9/20/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 9/28/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/28/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/31/2022 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 10/31/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 1/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 1/26/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 1/26/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/2/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 2/2/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/2/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 2/2/2023 | Approved | EUGENE CASSIDY |
| Insulation | 2/27/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/27/2023 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 3/7/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/7/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 3/16/2023 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 6/22/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | EUGENE CASSIDY |
| Final | 10/6/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/6/2023 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/6/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 10/6/2023 | Approved | EUGENE CASSIDY |
| Final | 10/17/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/17/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/30/2023 | Approved | EUGENE CASSIDY |
| Final | 10/30/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/30/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/30/2023 | Approved | EUGENE CASSIDY |