21147 S DALTON AVE 90501

Certificate Information: 21147 S DALTON AVE 90501

Application / Permit
21014-30000-00812
Plan Check / Job No.
B21WL00794
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Remodel to (E) 1-Story S.F.D
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 DAVID CASTILLO
Corrections Issued 4/7/2021 DAVID CASTILLO
Quality Review Completed 4/16/2021 TARIK SAOUD
Applicant returned to address corrections 8/18/2021 DAVID CASTILLO
Applicant returned to address corrections 11/5/2021 DAVID CASTILLO
Plan Check Approved 11/18/2021 DAVID CASTILLO
Building Plans Picked Up 11/19/2021 APPLICANT
Issued 3/25/2022 APPLICANT
CofO in Progress 10/31/2023 EUGENE CASSIDY
CofO Issued 11/3/2023 ANSON MAGLASANG
Permit Finaled 11/3/2023 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 5/26/2021 CHINH DINH
Grading Pre-Inspection Cleared 6/4/2021 KIRK LINKLATER
Low Impact Development Cleared 10/27/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/9/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/17/2021 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Mokri-Arganeh,, Fattaneh; Lic. No.: C52608 2075 S COUNTRY CYN RD      HACIENDA HEIGHTS, CA 91745

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2022 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 9/20/2022 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 9/28/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 9/28/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/21/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 10/31/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 10/31/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/26/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 1/26/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/26/2023 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 1/26/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 2/2/2023 Approved EUGENE CASSIDY
HVAC-Rough 2/2/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 2/2/2023 Approved EUGENE CASSIDY
Wood Frame 2/2/2023 Approved EUGENE CASSIDY
Insulation 2/27/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/27/2023 Partial Approval EUGENE CASSIDY
Drywall Nailing 3/7/2023 Approved EUGENE CASSIDY
Green Building Rough 3/7/2023 Approved EUGENE CASSIDY
Shower Pan 3/16/2023 Corrections Issued EUGENE CASSIDY
Sewer 6/22/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/6/2023 Approved EUGENE CASSIDY
Final 10/6/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/6/2023 Approved EUGENE CASSIDY
Green Building Final 10/6/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 10/6/2023 Approved EUGENE CASSIDY
Final 10/17/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 10/17/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved EUGENE CASSIDY
ELECTRICAL-Final 10/30/2023 Approved EUGENE CASSIDY
Final 10/30/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 10/30/2023 Approved EUGENE CASSIDY
PLUMBING-Final 10/30/2023 Approved EUGENE CASSIDY