2816 S STONER AVE 90064
Certificate Information: 2816 S STONER AVE 90064
- Application / Permit
- 21014-30000-00780
- Plan Check / Job No.
- B21WL00752
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor, and car port addition to (E) 1 story SFD
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 6/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 3/19/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 3/25/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/9/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 12/23/2021 | FELIPE HERNANDEZ |
| Issued | 3/1/2022 | APPLICANT |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| CofO in Progress | 5/11/2023 | JOHNNY MIRANDA |
| Permit Finaled | 6/1/2023 | DANIEL ORRANTE |
| CofO Issued | 6/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/14/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/15/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 10/21/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiang,, Tzuu Pien; Lic. No.: C72618 | 5399 STARLING DR JURUPA VALLEY, CA 91752 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/19/2022 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Conditional Approval | HERBERT GIRON |
| Insulation | 7/11/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/11/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 7/12/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 10/13/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 10/13/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 10/13/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/24/2022 | Corrections Issued | KENNETH NAGLE |
| HVAC-Rough | 10/24/2022 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 10/24/2022 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 10/26/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 10/26/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/26/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 11/4/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 11/4/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 11/14/2022 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/14/2022 | Partial Inspection | CLAYTON GRAHAM |
| Shower Pan | 11/14/2022 | Corrections Issued | CLAYTON GRAHAM |
| Drywall Nailing | 11/16/2022 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/30/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 11/30/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 12/14/2022 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 3/7/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 3/7/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 3/7/2023 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/14/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 3/14/2023 | Approved | CLAYTON GRAHAM |
| Final | 4/13/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/10/2023 | OK to Issue CofO | JOHNNY MIRANDA |
| Special/Order Compliance | 5/30/2023 | Corrections Issued | KENNETH NAGLE |