26341 S ZEPHYR AVE 90710

Certificate Information: 26341 S ZEPHYR AVE 90710

Application / Permit
21014-30000-00728
Plan Check / Job No.
B21WL00705
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Converting existing garage to ADU. PER GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 8/4/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 RICHARD GARCIA
Corrections Issued 2/27/2021 RICHARD GARCIA
Applicant returned to address corrections 7/19/2021 RICHARD GARCIA
Applicant returned to address corrections 9/3/2021 RICHARD GARCIA
Applicant returned to address corrections 3/15/2022 ALFREDO JARA
Applicant returned to address corrections 5/7/2022 JASON JANGADA
Plan Check Approved 6/13/2022 RICHARD GARCIA
Issued 8/4/2022 APPLICANT
CofO in Progress 4/25/2024 EUGENE CASSIDY
Permit Finaled 5/1/2024 ANSON MAGLASANG
CofO Issued 5/1/2024 ANSON MAGLASANG
Permit Finaled 5/1/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/2/2021 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 11/2/2021 JOSE HERNANDEZ
Sewer availability Cleared 11/2/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 11/12/2021 JOSE HERNANDEZ
Construction near power lines Cleared 1/8/2022 RIDWAN HARDY
Construction within easement Cleared 1/8/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 1/21/2022 GILBERT URREA
ZI Cleared 3/3/2022 RYAN LY
Grading Pre-Inspection Cleared 6/13/2022 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Namvar,, Mohammad Alipour; Lic. No.: C39797 231 VISTA DEL MAR STE D      REDONDO BEACH, CA 90277

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/11/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/11/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/11/2022 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 8/15/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/22/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/22/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/29/2022 Approved EUGENE CASSIDY
Green Building Rough 8/29/2022 Approved EUGENE CASSIDY
Drywall Nailing 11/28/2022 Approved ANSON MAGLASANG
Insulation 11/28/2022 Approved ANSON MAGLASANG
Final 1/31/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 1/31/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 1/31/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 4/10/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 10/16/2023 No Access for Inspection EUGENE CASSIDY
Grounding or Bonding 10/16/2023 No Access for Inspection EUGENE CASSIDY
Smoke Detectors 10/16/2023 Corrections Issued EUGENE CASSIDY
Final 10/17/2023 Corrections Issued EUGENE CASSIDY
Smoke Detectors 10/17/2023 Approved EUGENE CASSIDY
Final 3/20/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 3/20/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/24/2024 Approved EUGENE CASSIDY
Final 4/24/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/24/2024 Approved EUGENE CASSIDY
PLUMBING-Final 4/24/2024 Approved EUGENE CASSIDY
Service/Power Release 4/24/2024 Not Required EUGENE CASSIDY