1426 N GULF AVE 90744
Certificate Information: 1426 N GULF AVE 90744
- Application / Permit
- 21014-30000-00697
- Plan Check / Job No.
- B21WL00675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) S.F.D. Per engineering design.
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 1/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | RICHARD GARCIA |
| Corrections Issued | 2/27/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/2/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 5/12/2021 | DAVID CASTILLO |
| Plan Check Approved | 5/21/2021 | ALFREDO JARA |
| No Progress | 5/21/2021 | ALFREDO JARA |
| Plan Check Approved | 5/21/2021 | ALFREDO JARA |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 1/9/2024 | EUGENE CASSIDY |
| Permit Finaled | 1/9/2024 | ANSON MAGLASANG |
| CofO Issued | 1/9/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/9/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/8/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2021 | CHINH DINH |
Contact Information
| Contractor | A B S Construction Group Inc; Lic. No.: 891322-B | 1133 S SWALL DR LOS ANGELES, CA 90035 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/5/2021 | No Access for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 8/6/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 8/6/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 8/6/2021 | Approved | JOHN KLARIN |
| Wood Frame | 8/18/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 9/8/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 9/8/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | CRAIG DAVIS |
| Insulation | 9/15/2021 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 9/15/2021 | Approved | CRAIG DAVIS |
| Wood Frame | 9/15/2021 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 9/23/2021 | Approved | CRAIG DAVIS |
| Final | 11/15/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 11/15/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 11/15/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/8/2024 | Approved | EUGENE CASSIDY |
| Final | 1/8/2024 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 1/8/2024 | Approved | EUGENE CASSIDY |
| HVAC-Final | 1/8/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/8/2024 | Approved | EUGENE CASSIDY |