122 N CARMELINA AVE 90049

Certificate Information: 122 N CARMELINA AVE 90049

Application / Permit
21014-30000-00675
Plan Check / Job No.
B21WL00655
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and interior remodel to (E) SFD. Per engineering design.
Permit Issued
Issued on 7/16/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/23/2021 JASON JANGADA
Corrections Issued 2/26/2021 JASON JANGADA
Applicant returned to address corrections 4/13/2021 MARJAN SHENASI
Applicant returned to address corrections 5/17/2021 ALFREDO JARA
Applicant returned to address corrections 7/3/2021 ALFREDO JARA
Plan Check Approved 7/8/2021 ALFREDO JARA
Issued 7/16/2021 APPLICANT
CofO in Progress 3/8/2022 BRENDAN LOONEY
Permit Finaled 4/28/2022 DANIEL ORRANTE
Permit Finaled 4/28/2022 DANIEL ORRANTE
CofO Issued 4/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/8/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/8/2021 DINAH GARIN
Sewer availability Cleared 3/8/2021 DINAH GARIN
Grading Pre-Inspection Cleared 4/28/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/13/2021 No Result Entered DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 8/18/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/18/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 8/27/2021 Partial Approval JUAN VALENZUELA
Wood Frame 8/27/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 9/7/2021 No Result Entered DANNY TOLENTINO
Footing/Foundation/Slab 9/8/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/14/2021 Partial Approval JUAN VALENZUELA
HVAC-Rough 10/14/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 10/14/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval JUAN VALENZUELA
Wood Frame 10/18/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Approved JUAN VALENZUELA
Insulation 10/22/2021 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 10/22/2021 Partial Approval JUAN VALENZUELA
Insulation 10/26/2021 Approved JUAN VALENZUELA
Drywall Nailing 11/12/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/22/2021 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 2/25/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 2/25/2022 Corrections Issued JUAN VALENZUELA
Final 2/25/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 2/25/2022 Approved JUAN VALENZUELA
Green Building Rough 2/25/2022 Approved JUAN VALENZUELA
HVAC-Final 2/25/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 2/25/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 2/25/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 3/3/2022 Approved JUAN VALENZUELA
HVAC-Final 3/3/2022 Approved JUAN VALENZUELA
Final 3/7/2022 OK to Issue CofO BRENDAN LOONEY