15114 W HARTSOOK ST 91403
Certificate Information: 15114 W HARTSOOK ST 91403
- Application / Permit
- 21014-30000-00604
- Plan Check / Job No.
- B21WL00621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Front and rear addition to an existing SFD. Kitchen remodel. All new windows & doors.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | RICHARD GARCIA |
| Corrections Issued | 2/21/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/5/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Plan Check Approved | 3/17/2021 | ALFREDO JARA |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | JACK KARGODORIAN |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
| CofO Issued | 8/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 3/1/2021 | LAUREN PADICK |
Contact Information
| Contractor | Karma Remodel & Development Inc; Lic. No.: 875130-B | 21610 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2021 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/21/2021 | Corrections Issued | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/7/2021 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 6/11/2021 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 7/22/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 7/26/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 7/26/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 7/26/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 8/5/2021 | Partial Approval | ALAN MORELOS |
| Insulation | 8/10/2021 | Corrections Issued | ALAN MORELOS |
| Insulation | 8/12/2021 | Approved | AMY COLIN |
| Drywall Nailing | 8/24/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/24/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | JACK KARGODORIAN |
| Final | 11/4/2021 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/4/2021 | Approved | JACK KARGODORIAN |
| Green Building Final | 11/4/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 11/4/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/4/2021 | Approved | JACK KARGODORIAN |
| Final | 11/15/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/29/2021 | OK to Issue CofO | JACK KARGODORIAN |