ADU (607 sf) addition to (e) detached 1-car garage (216 sf) at rear of the lot per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/19/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 FELIPE HERNANDEZ
Corrections Issued 2/22/2021 FELIPE HERNANDEZ
Quality Review Completed 3/5/2021 TARIK SAOUD
Applicant returned to address corrections 9/24/2021 FELIPE HERNANDEZ
Plan Check Approved 12/13/2023 REZA HAGHIGHAT
Issued 12/19/2023 APPLICANT
CofO in Progress 8/26/2025 JOSEPH MCGARRY
CofO Issued 8/26/2025 ANSON MAGLASANG
Permit Finaled 8/26/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/13/2021 ERIK BEASLEY
BHO/Hillside ordinance Cleared 10/13/2021 ERIK BEASLEY
BHO/Hillside ordinance Cleared 10/13/2021 ERIK BEASLEY
BHO/Hillside ordinance Cleared 10/13/2021 ERIK BEASLEY
BHO/Hillside ordinance Cleared 10/13/2021 ERIK BEASLEY
BHO/Hillside ordinance Cleared 10/13/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/6/2022 ERIK BEASLEY
Sewer availability Cleared 1/6/2022 ERIK BEASLEY
Low Impact Development Cleared 9/22/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/12/2023 KHAING AYE
Grading Pre-Inspection Cleared 12/13/2023 FELIPE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Afshar,, Hooshang A; Lic. No.: C61157 17 COROZAL      FOOTHILL RANCH, CA 92610

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/8/2025 Approved JOSEPH MCGARRY
Underground Mechanical 1/8/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 1/23/2025 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 1/23/2025 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 5/9/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 5/9/2025 Approved JOSEPH MCGARRY
Green Building Rough 5/9/2025 Approved JOSEPH MCGARRY
HVAC-Rough 5/9/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/9/2025 Approved JOSEPH MCGARRY
Underground Mechanical 5/9/2025 Approved JOSEPH MCGARRY
Insulation 5/12/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 5/14/2025 Approved JOSEPH MCGARRY
Drywall Nailing 5/16/2025 Partial Approval JOSEPH MCGARRY
Shower Pan 5/16/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/19/2025 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 5/21/2025 Approved JOSEPH MCGARRY
Drywall Nailing 6/10/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/25/2025 Approved JOSEPH MCGARRY
Gas Test 7/25/2025 Approved JOSEPH MCGARRY
Green Building Final 7/25/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 7/25/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 7/25/2025 Approved JOSEPH MCGARRY
Smoke Detectors 7/25/2025 Approved JOSEPH MCGARRY
Final 7/29/2025 Corrections Issued JOSEPH MCGARRY
Special/Order Compliance 8/7/2025 Approved BEN MOLSTAD
Final 8/25/2025 OK to Issue CofO JOSEPH MCGARRY