1536 N ORANGE GROVE AVE 90046

Certificate Information: 1536 N ORANGE GROVE AVE 90046

Application / Permit
21014-30000-00561
Plan Check / Job No.
B21WL00579
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND FLOOR ADDITION AND REMODEL TO EXISTING 2-ST0RY TYPE VB SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/25/2021
Issuing Office
Current Status
CofO Issued on 10/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 SERGIO SILVA
Corrections Issued 3/3/2021 SERGIO SILVA
Quality Review Completed 3/12/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/12/2021 SERGIO SILVA
Applicant returned to address corrections 6/16/2021 SERGIO SILVA
Plan Check Approved 7/22/2021 SERGIO SILVA
No Progress 7/22/2021 SERGIO SILVA
Plan Check Approved 8/18/2021 SERGIO SILVA
Issued 8/25/2021 APPLICANT
CofO in Progress 9/21/2022 RAUL BARAJAS
Permit Finaled 10/3/2022 DEROLD HAUFF
CofO Issued 10/3/2022 DEROLD HAUFF
Permit Finaled 10/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/19/2021 CELINA MORENO
Permit Cleared 3/19/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 3/19/2021 CELINA MORENO
Sewer availability Cleared 3/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 CELINA MORENO
Hydrant and Access approval Cleared 4/25/2021 KURT CORRAL
CPC Cleared 5/5/2021 AMANDA KAINER
HPOZ Cleared 5/5/2021 AMANDA KAINER
Miscellaneous Cleared 5/5/2021 AMANDA KAINER
ZI Cleared 5/5/2021 AMANDA KAINER
Trees in Parkway Cleared 7/15/2021 JOHN KIM
Green Code Cleared 7/22/2021 SERGIO SILVA

Contact Information

Contractor H & O Unique Construction Inc; Lic. No.: 1016124-B 16350 VENTURA BLVD #106      ENCINO, CA 91436

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Approved RAUL BARAJAS
Insulation 9/10/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval RAUL BARAJAS
Green Building Rough 9/17/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 10/15/2021 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 10/15/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved RAUL BARAJAS
Green Building Rough 10/15/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 10/15/2021 Approved RAUL BARAJAS
Deputy Wood Construction 10/19/2021 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 10/19/2021 Approved RAUL BARAJAS
HVAC-Rough 10/19/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 10/19/2021 Approved RAUL BARAJAS
Insulation 10/27/2021 Conditional Approval RAUL BARAJAS
Interior/Exterior Lathing 10/27/2021 Conditional Approval RAUL BARAJAS
Drywall Nailing 11/3/2021 Approved RAUL BARAJAS
Green Building Rough 11/3/2021 Approved RAUL BARAJAS
HVAC-Final 11/3/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 5/26/2022 Approved RAUL BARAJAS
Final 5/26/2022 Corrections Issued RAUL BARAJAS
Green Building Final 5/26/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 5/26/2022 Approved RAUL BARAJAS
Final 6/16/2022 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Approved RAUL BARAJAS
Final 9/21/2022 OK to Issue CofO RAUL BARAJAS