7718 S EMERSON AVE 90045

Certificate Information: 7718 S EMERSON AVE 90045

Application / Permit
21014-30000-00552
Plan Check / Job No.
B21WL00545
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel (E)SFD. Per engineering design.
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
Issued on 5/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2021 APPLICANT
Assigned to Plan Check Engineer 2/16/2021 ALFREDO JARA
Corrections Issued 2/17/2021 ALFREDO JARA
Plan Check Approved 5/21/2021 ALFREDO JARA
Issued 5/26/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/13/2021 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 4/13/2021 NIKTA MOUSAVI
GPI Written Notices Cleared 5/21/2021 ALFREDO JARA
Grading Pre-Inspection Cleared 5/21/2021 ALFREDO JARA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/21/2021 Partial Approval DONALD GALLAGHER
METHANE-Barrier 6/21/2021 Conditional Approval DONALD GALLAGHER
METHANE-Subgrade 6/21/2021 Conditional Approval DONALD GALLAGHER
BUILDING-Rough-Frame 6/29/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 6/29/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 6/29/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/28/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/28/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Approved ENRIQUE MIRELES
Green Building Rough 7/28/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/24/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/24/2021 Approved JOHNNY MIRANDA
Insulation 8/27/2021 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 8/27/2021 Corrections Issued BRENDAN LOONEY
Insulation 9/3/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/3/2021 Corrections Issued JOHNNY MIRANDA
Drywall Nailing 9/13/2021 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Final 3/26/2025 Approved RUBEN RIVAS
HVAC-Final 3/26/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Final 3/26/2025 Corrections Issued RUBEN RIVAS
Special/Order Compliance 3/26/2025 Partial Inspection BOBBY KEY
Interior/Exterior Lathing 4/3/2025 Approved RUBEN RIVAS