4247-4247 1/2 W 58TH PL 90043
Certificate Information: 4247-4247 1/2 W 58TH PL 90043
- Application / Permit
- 21014-30000-00548
- Plan Check / Job No.
- B21WL00535
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADU addition to (E) Single family dwelling per ordinance. per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2021 | KAVIAN REFAHI |
| Corrections Issued | 2/27/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/28/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 2/24/2022 | MARJAN SHENASI |
| Plan Check Approved | 3/11/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 1/29/2024 | ENRIQUE MIRELES |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
| CofO Issued | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/2/2021 | RIDWAN HARDY |
| Address approval | Cleared | 1/4/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/18/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 2/8/2022 | EDWIN ESPIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2022 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 4/1/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 4/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/6/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 4/6/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | HORACE FULTZ |
| PLUMBING-Rough | 4/15/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/30/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 8/30/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/27/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/27/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 4/5/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/5/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/12/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/22/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/22/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/22/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/4/2024 | OK to Issue CofO | ENRIQUE MIRELES |