2749 S WESTGATE AVE 90064

Certificate Information: 2749 S WESTGATE AVE 90064

Application / Permit
21014-30000-00535
Plan Check / Job No.
B21WL00511
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st floor- expand family room; add stairs to new 2nd floor 2nd floor- new 2nd floor w/ 2 bedrooms and 1 bath
Permit Issued
Issued on 2/3/2022
Issuing Office
Current Status
CofO Issued on 12/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 HOOMAN HAJIZADEH
Corrections Issued 3/17/2021 HOOMAN HAJIZADEH
Quality Review Completed 3/26/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/28/2021 HOOMAN HAJIZADEH
Applicant returned to address corrections 10/8/2021 HOOMAN HAJIZADEH
Applicant returned to address corrections 12/10/2021 HOOMAN HAJIZADEH
Plan Check Approved 12/17/2021 HOOMAN HAJIZADEH
Building Plans Picked Up 12/20/2021 APPLICANT
Issued 2/3/2022 APPLICANT
CofO in Progress 11/28/2022 DAVID FEILER
Permit Finaled 12/1/2022 DANIEL ORRANTE
CofO Issued 12/1/2022 DANIEL ORRANTE
Permit Finaled 12/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/19/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/20/2021 DINAH GARIN
Sewer availability Cleared 8/20/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/7/2021 DINAH GARIN
Specific Plan Cleared 9/28/2021 PETE EYRE

Contact Information

Contractor Precise Home Builders Inc; Lic. No.: 515469-B 6925 CANBY AVE STE #103      RESEDA, CA 91335
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 4/7/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 4/7/2022 Approved JOHNNY MIRANDA
Green Building Rough 4/7/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 4/7/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/7/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 4/12/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Approved JOHNNY MIRANDA
Green Building Rough 4/12/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 4/12/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 4/12/2022 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 4/22/2022 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/25/2022 Approved JOHNNY MIRANDA
Green Building Rough 4/25/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/25/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/25/2022 Approved JOHNNY MIRANDA
Insulation 4/27/2022 Corrections Issued JOHNNY MIRANDA
Insulation 4/28/2022 Approved JOHNNY MIRANDA
Drywall Nailing 5/5/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/5/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/22/2022 Approved JOHNNY MIRANDA
Final 7/22/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 7/22/2022 Approved JOHNNY MIRANDA
HVAC-Final 7/22/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 7/22/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/22/2022 Approved JOHNNY MIRANDA
Final 8/11/2022 Corrections Issued JOHNNY MIRANDA
Final 11/28/2022 OK to Issue CofO DAVID FEILER
HVAC-Final 11/28/2022 Approved DAVID FEILER