9825 W ALTMAN AVE 90034

Certificate Information: 9825 W ALTMAN AVE 90034

Application / Permit
21014-30000-00523
Plan Check / Job No.
B21WL00498
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition to (e) 1-story SFD w./ att. 2-car garage
Permit Issued
Issued on 8/26/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 REZA HAGHIGHAT
Corrections Issued 3/3/2021 REZA HAGHIGHAT
Building Plans Picked Up 3/5/2021 APPLICANT
Quality Review Completed 3/12/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/16/2021 REZA HAGHIGHAT
Issued 8/26/2021 APPLICANT
CofO in Progress 5/3/2023 CLAYTON GRAHAM
Permit Finaled 5/4/2023 DANIEL ORRANTE
CofO Issued 5/4/2023 DANIEL ORRANTE
Permit Finaled 5/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/15/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/15/2021 HISASHI KOBAYAKAWA
Low Impact Development Cleared 7/30/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/3/2021 ANTHONY MAINEZ
GPI Written Notices Cleared 8/16/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/16/2021 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor C R J Construction; Lic. No.: 1025947-B 23679 CALABASAS RD #973      CALABASAS, CA 91302
Engineer Gruenbaum,, Nathan Henry; Lic. No.: C22262 6337 LINDENHURST AVENUE      LOS ANGELES, CA 90048
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 10/27/2021 Partial Inspection KENNETH NAGLE
Pre-Inspection 1/7/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 1/18/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/20/2022 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Barrier 1/20/2022 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 1/20/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 1/24/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/26/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 1/26/2022 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Subgrade 1/26/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Steel/Welding 2/14/2022 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/15/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 8/2/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/5/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/5/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/9/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 8/9/2022 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/12/2022 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 8/12/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 8/12/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/12/2022 Approved OGANES TARAKHCHYAN
Insulation 8/19/2022 Approved OGANES TARAKHCHYAN
Shower Pan 8/19/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/24/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 8/30/2022 Approved OGANES TARAKHCHYAN
Sewer 3/2/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/3/2023 Not Ready for Inspection ASHLEY THOMPSON
Service/Power Release 3/3/2023 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 3/3/2023 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 3/16/2023 Partial Approval CARLOS MATAMOROS
Gas Test 3/16/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 3/16/2023 Partial Approval CARLOS MATAMOROS
Service/Power Release 3/16/2023 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 3/22/2023 Approved ASHLEY THOMPSON
HVAC-Final 3/22/2023 Approved ASHLEY THOMPSON
PLUMBING-Final 3/22/2023 Approved ASHLEY THOMPSON
Service/Power Release 3/24/2023 Approved DAVID FEILER
BUILDING-Rough-Frame 4/6/2023 Approved ASHLEY THOMPSON
Final 4/6/2023 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 4/6/2023 Approved ASHLEY THOMPSON
Green Building Final 4/6/2023 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 4/6/2023 Approved ASHLEY THOMPSON
METHANE-Subgrade 4/6/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 4/6/2023 Corrections Issued ASHLEY THOMPSON
Final 4/12/2023 Corrections Issued JEREMY TODD
Green Building Final 4/12/2023 Approved JEREMY TODD
Smoke Detectors 4/12/2023 Approved JEREMY TODD
Final 4/28/2023 OK to Issue CofO CLAYTON GRAHAM