9825 W ALTMAN AVE 90034
Certificate Information: 9825 W ALTMAN AVE 90034
- Application / Permit
- 21014-30000-00523
- Plan Check / Job No.
- B21WL00498
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition to (e) 1-story SFD w./ att. 2-car garage
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 3/3/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Quality Review Completed | 3/12/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/16/2021 | REZA HAGHIGHAT |
| Issued | 8/26/2021 | APPLICANT |
| CofO in Progress | 5/3/2023 | CLAYTON GRAHAM |
| Permit Finaled | 5/4/2023 | DANIEL ORRANTE |
| CofO Issued | 5/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/15/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 7/30/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 8/16/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 8/16/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | C R J Construction; Lic. No.: 1025947-B | 23679 CALABASAS RD #973 CALABASAS, CA 91302 |
| Engineer | Gruenbaum,, Nathan Henry; Lic. No.: C22262 | 6337 LINDENHURST AVENUE LOS ANGELES, CA 90048 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 10/27/2021 | Partial Inspection | KENNETH NAGLE |
| Pre-Inspection | 1/7/2022 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/20/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Barrier | 1/20/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 1/20/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/24/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 1/26/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 1/26/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 2/14/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/5/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/5/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 8/12/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 8/12/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/12/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/24/2022 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 8/30/2022 | Approved | OGANES TARAKHCHYAN |
| Sewer | 3/2/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 3/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 3/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/16/2023 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 3/16/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/16/2023 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/22/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 3/22/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 3/22/2023 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 3/24/2023 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 4/6/2023 | Approved | ASHLEY THOMPSON |
| Final | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 4/6/2023 | Approved | ASHLEY THOMPSON |
| Green Building Final | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 4/6/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 4/6/2023 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 4/6/2023 | Corrections Issued | ASHLEY THOMPSON |
| Final | 4/12/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 4/12/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 4/12/2023 | Approved | JEREMY TODD |
| Final | 4/28/2023 | OK to Issue CofO | CLAYTON GRAHAM |