2370 N TEVIOT ST 90039
Certificate Information: 2370 N TEVIOT ST 90039
- Application / Permit
- 21014-30000-00469
- Plan Check / Job No.
- B21WL00469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 1st and 2nd story deck addition to an existing duplex. Kitchen remodel of lower unit.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RICHARD GARCIA |
| Corrections Issued | 2/13/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 3/26/2021 | RICHARD GARCIA |
| Issued | 4/5/2021 | APPLICANT |
| CofO in Progress | 1/24/2022 | THOMAS LOGRASSO |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
| CofO Issued | 3/2/2022 | DEROLD HAUFF |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/9/2021 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 3332 BENNETT DRIVE LOS ANGELES, CA 90068 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/22/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/30/2021 | Approved | ROBERT VORHIS |
| Deputy Reinf. Concrete | 7/6/2021 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 12/13/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 12/14/2021 | Partial Approval | RUBEN SALAS |
| Deputy Wood Construction | 12/14/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/15/2021 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 12/15/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Wood Construction | 12/20/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/21/2021 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/29/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/29/2021 | Approved | THOMAS LOGRASSO |
| Gas Test | 12/29/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/29/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/29/2021 | Approved | THOMAS LOGRASSO |
| Final | 1/21/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 1/21/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 1/21/2022 | Approved | THOMAS LOGRASSO |