5860 N ALCOVE AVE 91607

Certificate Information: 5860 N ALCOVE AVE 91607

Application / Permit
21014-30000-00430
Plan Check / Job No.
B21WL00447
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to living room (137 sf), convert (E) family room to master suite with new master bathroom. Remodel (E) powder room, remove (E) wall between kitchen and dining with new beam. Convert (E) bedroom #4 to family room. Per engineering design.
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 10/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 ALFREDO JARA
Corrections Issued 2/9/2021 ALFREDO JARA
Applicant returned to address corrections 3/4/2021 ALFREDO JARA
Building Plans Picked Up 3/4/2021 APPLICANT
Plan Check Approved 3/26/2021 ALFREDO JARA
Issued 4/5/2021 APPLICANT
CofO in Progress 9/16/2024 OGANES TARAKHCHYAN
CofO Issued 10/8/2024 DANIEL ORRANTE
Permit Finaled 10/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2021 ADRIAN CASTRO
ZA Case Cleared 3/11/2021 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/6/2021 No Result Entered GREG ALLTON
ELECTRICAL-Rough 4/19/2021 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 4/19/2021 Approved RICHARD DOCKUS
HVAC-Rough 4/26/2021 Approved RICHARD DOCKUS
Insulation 4/26/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 4/26/2021 Partial Approval RICHARD DOCKUS
Shower Pan 4/26/2021 Approved RICHARD DOCKUS
Drywall Nailing 4/29/2021 Approved RICHARD DOCKUS
Green Building Rough 4/29/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/6/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 9/6/2024 Approved OGANES TARAKHCHYAN
Final 9/6/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 9/6/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 9/6/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 9/6/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 9/6/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 9/13/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/13/2024 Approved OGANES TARAKHCHYAN