1507 N BUNDY DR 90049
Certificate Information: 1507 N BUNDY DR 90049
- Application / Permit
- 21014-30000-00354
- Plan Check / Job No.
- B21WL00384
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to (e) 1-story SFD w./ att. 2-car garage
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 2/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | REZA HAGHIGHAT |
| Corrections Issued | 2/17/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 2/22/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/13/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 7/7/2021 | REZA HAGHIGHAT |
| Issued | 7/14/2021 | APPLICANT |
| CofO in Progress | 12/12/2022 | STEPHANIE SWANSON |
| Permit Finaled | 2/3/2023 | DANIEL ORRANTE |
| CofO Issued | 2/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/8/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/9/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 5/13/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 5/13/2021 | REZA HAGHIGHAT |
| Low Impact Development | Cleared | 7/2/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/7/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 7/7/2021 | MAHELET GEBEYHU |
Contact Information
| Contractor | Shirley David M Construction Corporation; Lic. No.: 602138-B | 11693 SAN VICENTE BLVE #905 LOS ANGELES, CA 90049 |
| Engineer | Shirley,, Peter Franklin; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 7/26/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/26/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 7/26/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 8/19/2021 | Conditional Approval | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | JUAN VALENZUELA |
| Grading Pre-Inspection | 9/15/2021 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 11/12/2021 | Partial Approval | ANDREW NAVE |
| FLOOD-Elevation Certificate | 11/22/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/22/2021 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 12/15/2021 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2022 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/15/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 2/15/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 2/16/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 2/17/2022 | Corrections Issued | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 3/1/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 3/1/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/1/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 3/1/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 3/24/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/24/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/24/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 3/24/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/19/2022 | Corrections Issued | JUAN VALENZUELA |
| Service/Power Release | 5/19/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/20/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/20/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 5/20/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 5/23/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 5/25/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | JUAN VALENZUELA |
| Final | 6/23/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 6/23/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 6/23/2022 | Approved | JUAN VALENZUELA |
| Final | 12/12/2022 | OK to Issue CofO | STEPHANIE SWANSON |