8933 W 24TH ST 90034

Certificate Information: 8933 W 24TH ST 90034

Application / Permit
21014-30000-00316
Plan Check / Job No.
B21WL00348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story master bath and closet addition to (e) single story SFD
Permit Issued
Issued on 7/17/2021
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 REZA HAGHIGHAT
Corrections Issued 2/17/2021 REZA HAGHIGHAT
Quality Review Completed 2/22/2021 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/25/2021 APPLICANT
Plan Check Approved 6/9/2021 REZA HAGHIGHAT
Issued 7/17/2021 APPLICANT
CofO in Progress 7/29/2022 EVAN COOPER
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/9/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 4/13/2021 THOMAS LANG
Low Impact Development Cleared 5/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/10/2021 THOMAS LANG

Contact Information

Architect , ; Lic. No.: C34605    4023 MOORE STREET    LOS ANGELES, CA 90066
Contractor K S Construction And Design; Lic. No.: 896510-B 22100 BURBANK BL #226C      WOODLAND HILLS, CA 91367
Engineer Vahabzadeh,, Reza; Lic. No.: S6538 13961 MOORPARK ST APT 207      SHERMAN OAKS, CA 91423

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2021 Approved EVAN COOPER
Deputy Drilled-In Anchors 8/30/2021 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/1/2021 Approved EVAN COOPER
Footing/Foundation/Slab 9/1/2021 Approved EVAN COOPER
Insulation 9/10/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 9/10/2021 Partial Approval EVAN COOPER
Wood Frame 9/10/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 9/28/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 9/28/2021 Approved EVAN COOPER
Green Building Rough 9/28/2021 Not Ready for Inspection EVAN COOPER
HVAC-Rough 9/28/2021 Approved EVAN COOPER
PLUMBING-Rough 9/28/2021 Approved EVAN COOPER
Wood Frame 9/28/2021 Conditional Approval EVAN COOPER
Green Building Rough 10/7/2021 Not Ready for Inspection EVAN COOPER
Shower Pan 10/7/2021 Approved EVAN COOPER
Interior/Exterior Lathing 10/15/2021 Partial Approval EVAN COOPER
Interior/Exterior Lathing 10/21/2021 Not Ready for Inspection JOHNNY MIRANDA
Underground Mechanical 10/21/2021 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 10/26/2021 Partial Approval EVAN COOPER
Rough-Elec/Plmb/HVAC 12/21/2021 Approved EVAN COOPER
Wood Frame 12/21/2021 Approved EVAN COOPER
Insulation 12/23/2021 Approved EVAN COOPER
Drywall Nailing 12/29/2021 Approved EVAN COOPER
Green Building Rough 12/29/2021 Approved EVAN COOPER
ELECTRICAL-Final 3/7/2022 Not Ready for Inspection EVAN COOPER
Gas Test 3/7/2022 Approved EVAN COOPER
Underground Mechanical 3/7/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 7/1/2022 Approved EVAN COOPER
Final 7/1/2022 Corrections Issued EVAN COOPER
Green Building Final 7/1/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 7/1/2022 Approved EVAN COOPER
Final 7/26/2022 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Final 7/29/2022 Approved EVAN COOPER
Final 7/29/2022 OK to Issue CofO EVAN COOPER
HVAC-Final 7/29/2022 Approved EVAN COOPER
PLUMBING-Final 7/29/2022 Approved EVAN COOPER