1125 S CREST DR 90035

Certificate Information: 1125 S CREST DR 90035

Application / Permit
21014-30000-00305
Plan Check / Job No.
B21WL00340
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 290 sf addition to and interior renovation of (e) 2327 sf s.f.d. w/ (e) attached garage
Permit Issued
Issued on 5/11/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 RICHARD GARCIA
Corrections Issued 1/31/2021 RICHARD GARCIA
Building Plans Picked Up 2/4/2021 APPLICANT
Applicant returned to address corrections 4/13/2021 FELIPE HERNANDEZ
Plan Check Approved 4/27/2021 FELIPE HERNANDEZ
Issued 5/11/2021 APPLICANT
CofO in Progress 4/25/2022 EVAN COOPER
Permit Finaled 4/28/2022 DANIEL ORRANTE
CofO Issued 4/28/2022 DANIEL ORRANTE
Permit Finaled 4/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/24/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 4/20/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 4/20/2021 DINAH GARIN
Sewer availability Cleared 4/20/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Downey,, Henry Ross; Lic. No.: S2628 7463 VARNA AVE      NORTH HOLLYWOOD, CA 916054011

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/2/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 8/4/2021 Approved EVAN COOPER
METHANE-Barrier 8/4/2021 Approved EVAN COOPER
METHANE-Subgrade 8/4/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 10/29/2021 Approved EVAN COOPER
ELECTRICAL-Rough 11/12/2021 Approved KEVIN SARGSYAN
HVAC-Rough 11/12/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 11/12/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 11/17/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 11/17/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 11/17/2021 Approved JOHNNY MIRANDA
METHANE-Rough 11/17/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 11/17/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/29/2021 Approved EVAN COOPER
Green Building Rough 11/29/2021 Approved EVAN COOPER
Insulation 11/29/2021 Approved EVAN COOPER
METHANE-Rough 11/29/2021 Approved EVAN COOPER
Shower Pan 11/29/2021 Approved EVAN COOPER
Drywall Nailing 12/3/2021 Approved EVAN COOPER
Green Building Rough 12/3/2021 Approved EVAN COOPER
Interior/Exterior Lathing 12/3/2021 Partial Approval EVAN COOPER
Interior/Exterior Lathing 12/14/2021 Approved EVAN COOPER
ELECTRICAL-Rough 1/20/2022 Approved EVAN COOPER
ELECTRICAL-Final 2/18/2022 Corrections Issued DEANDRE HOFFMAN
HVAC-Final 2/18/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Final 2/18/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 3/17/2022 Approved OGANES TARAKHCHYAN
Green Building Final 3/17/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 3/17/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 3/17/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/22/2022 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 4/22/2022 Approved EVAN COOPER