1133 E VAN BUREN AVE 90291

Certificate Information: 1133 E VAN BUREN AVE 90291

Application / Permit
21014-30000-00291
Plan Check / Job No.
B21WL00321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd story addition & major remodel of (E) 1 story SFD.
Permit Issued
Issued on 9/21/2021
Issuing Office
Current Status
CofO Issued on 7/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 2/11/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 2/19/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/28/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 9/17/2021 MANUEL GARCIA
Issued 9/21/2021 APPLICANT
CofO in Progress 7/21/2022 STEPHANIE SWANSON
Permit Finaled 7/25/2022 DANIEL ORRANTE
CofO Issued 7/25/2022 DANIEL ORRANTE
Permit Finaled 7/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/25/2021 CATHERINE ADROVER
Sewer availability Cleared 3/26/2021 CATHERINE ADROVER
Coastal Zone Cleared 6/11/2021 NOAH MCCOY
ZA Case Cleared 6/11/2021 NOAH MCCOY
ZA Case Cleared 6/11/2021 NOAH MCCOY
Specific Plan Cleared 6/15/2021 BINDU KANNAN
Low Impact Development Cleared 7/13/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/27/2021 DINAH GARIN

Contact Information

Architect Richardson,, Kari M; Lic. No.: C26982 642 FLOWER AVENUE      VENICE, CA 90291
Contractor Brunskill Construction Inc; Lic. No.: 847411-B 2711 N SEPULVEDA BLVD #410      MANHATTAN BEACH, CA 90266
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 10/26/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/3/2021 Approved KRISTEN CAUSEY
PLUMBING-Rough 11/15/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/18/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/2/2022 Approved ENRIQUE MIRELES
HVAC-Rough 2/2/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/10/2022 Approved ENRIQUE MIRELES
Green Building Rough 2/10/2022 Approved ENRIQUE MIRELES
Insulation 2/16/2022 Corrections Issued STEPHANIE SWANSON
Insulation 2/25/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/25/2022 Approved ENRIQUE MIRELES
Drywall Nailing 3/3/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/9/2022 Approved DAVID FEILER
Gas Test 6/9/2022 Approved PATRICK QUALEY
HVAC-Final 6/9/2022 Corrections Issued PATRICK QUALEY
HVAC-Final 6/15/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/16/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Approved PATRICK QUALEY
ELECTRICAL-Final 7/1/2022 Approved PATRICK QUALEY
Service/Power Release 7/1/2022 Not Ready for Inspection PATRICK QUALEY
Final 7/21/2022 OK to Issue CofO STEPHANIE SWANSON
Green Building Final 7/21/2022 Approved STEPHANIE SWANSON
Service/Power Release 7/21/2022 Approved STEPHANIE SWANSON
Smoke Detectors 7/21/2022 Approved STEPHANIE SWANSON