151 S CRESCENT HEIGHTS BLVD 90048

Certificate Information: 151 S CRESCENT HEIGHTS BLVD 90048

Application / Permit
21014-30000-00287
Plan Check / Job No.
B21WL00318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd story addition, att. 1-car garage addition and remodel to (e) single story SFD
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 REZA HAGHIGHAT
Corrections Issued 2/8/2021 REZA HAGHIGHAT
Quality Review Completed 2/19/2021 TARIK SAOUD
Applicant returned to address corrections 5/30/2021 REZA HAGHIGHAT
Plan Check Approved 7/1/2021 REZA HAGHIGHAT
Issued 8/16/2021 APPLICANT
Building Plans Picked Up 2/2/2022 APPLICANT
CofO in Progress 10/19/2022 EVAN COOPER
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 4/27/2021 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 4/28/2021 WALLIE JONG
Sewer availability Cleared 4/28/2021 WALLIE JONG
Low Impact Development Cleared 5/3/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 5/4/2021 WALLIE JONG

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/10/2021 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/4/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 10/4/2021 Partial Approval EVAN COOPER
METHANE-Barrier 10/4/2021 Approved EVAN COOPER
METHANE-Subgrade 10/4/2021 Approved EVAN COOPER
Footing/Foundation/Slab 10/8/2021 Approved EVAN COOPER
Underground Mechanical 10/22/2021 Approved OGANES TARAKHCHYAN
Underground Mechanical 10/28/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 11/16/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/22/2021 Partial Approval EVAN COOPER
Green Building Rough 11/22/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 11/22/2021 Not Ready for Inspection EVAN COOPER
Underground Mechanical 11/22/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 12/16/2021 Corrections Issued EVAN COOPER
Green Building Rough 12/16/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 12/16/2021 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 1/7/2022 Corrections Issued MICHAEL PELHAM
Deputy Wood Construction 2/15/2022 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 2/17/2022 Corrections Issued EVAN COOPER
Green Building Rough 2/17/2022 Not Ready for Inspection EVAN COOPER
METHANE-Rough 2/17/2022 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/9/2022 Partial Approval EVAN COOPER
Green Building Rough 5/9/2022 Not Ready for Inspection EVAN COOPER
METHANE-Rough 5/9/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 5/9/2022 Approved EVAN COOPER
PLUMBING-Rough 5/11/2022 Approved EVAN COOPER
ELECTRICAL-Rough 5/23/2022 Approved EVAN COOPER
HVAC-Rough 5/23/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/23/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 5/31/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Approved EVAN COOPER
Green Building Rough 5/31/2022 Approved EVAN COOPER
Wood Frame 5/31/2022 Approved EVAN COOPER
Drywall Nailing 6/13/2022 Approved EVAN COOPER
Insulation 6/13/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/14/2022 Approved EVAN COOPER
Shower Pan 6/14/2022 Approved EVAN COOPER
Gas Test 6/20/2022 Partial Approval DAVID FEILER
Underground Mechanical 8/22/2022 Partial Approval EVAN COOPER
Gas Test 10/3/2022 Approved EVAN COOPER
Service/Power Release 10/3/2022 Approved EVAN COOPER
ELECTRICAL-Final 10/5/2022 Approved EVAN COOPER
HVAC-Final 10/7/2022 Approved EVAN COOPER
PLUMBING-Final 10/12/2022 Approved EVAN COOPER
Final 10/19/2022 OK to Issue CofO EVAN COOPER
Green Building Final 10/19/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 10/19/2022 Approved EVAN COOPER