2617 S BARRY AVE 90064

Certificate Information: 2617 S BARRY AVE 90064

Application / Permit
21014-30000-00255
Plan Check / Job No.
B21WL00273
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 2-car garage to ADU and Addition per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 3/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 DAVID CASTILLO
Corrections Issued 2/1/2021 DAVID CASTILLO
Quality Review Completed 2/8/2021 TARIK SAOUD
Applicant returned to address corrections 6/29/2021 DAVID CASTILLO
Plan Check Approved 7/8/2021 DAVID CASTILLO
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/4/2022 APPLICANT
CofO in Progress 2/10/2023 JESUS RODRIGUEZ
No Progress 2/10/2023 RICHARD STEINBACH
Permit Finaled 3/11/2024 DANIEL ORRANTE
CofO Issued 3/11/2024 DANIEL ORRANTE
Permit Finaled 3/11/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/24/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 2/24/2021 DENNIS BRAGIN
Sewer availability Cleared 2/24/2021 DENNIS BRAGIN
Miscellaneous Cleared 3/2/2021 KEVIN ARUCAN
Roof/Waste drainage to street Cleared 6/8/2021 DENNIS BRAGIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 3/29/2022 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/21/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/21/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 6/28/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 8/17/2022 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval JOHNNY MIRANDA
Wood Frame 8/18/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 9/12/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 9/12/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 9/20/2022 Approved JOHN KIDWELL
HVAC-Rough 9/20/2022 Approved JOHN KIDWELL
PLUMBING-Rough 9/20/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/27/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved JOHNNY MIRANDA
Green Building Rough 9/27/2022 Approved JOHNNY MIRANDA
Insulation 9/27/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/27/2022 Partial Approval JOHNNY MIRANDA
MERV13>=Rough 9/27/2022 Approved JOHNNY MIRANDA
Drywall Nailing 10/4/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/4/2022 Approved JOHNNY MIRANDA
Shower Pan 10/4/2022 Corrections Issued JOHNNY MIRANDA
Shower Pan 10/7/2022 Approved JOHNNY MIRANDA
Gas Test 11/9/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/1/2023 Corrections Issued JOHNNY MIRANDA
Final 2/1/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 2/1/2023 Approved JOHNNY MIRANDA
HVAC-Final 2/1/2023 Approved JOHNNY MIRANDA
MERV13>=Final 2/1/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 2/1/2023 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 2/1/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/8/2023 Approved JESUS RODRIGUEZ
Final 2/8/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Final 2/8/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved JESUS RODRIGUEZ
Final 2/10/2023 Corrections Issued RICHARD STEINBACH