2615 S BARRY AVE 90064
Certificate Information: 2615 S BARRY AVE 90064
- Application / Permit
- 21014-30000-00253
- Plan Check / Job No.
- B21WL00273
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior Remodel and Addition to (E) S.F.D.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | DAVID CASTILLO |
| Corrections Issued | 2/1/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/8/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/29/2021 | DAVID CASTILLO |
| Plan Check Approved | 7/8/2021 | DAVID CASTILLO |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 5/28/2024 | JESUS PINEDA |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
| CofO Issued | 5/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 2/24/2021 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 6/8/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/8/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiang,, Tzuu Pien; Lic. No.: C72618 | 5399 STARLING DR JURUPA VALLEY, CA 91752 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2023 | Partial Inspection | DAVID FEILER |
| Special/Order Compliance | 7/3/2023 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 8/7/2023 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 8/8/2023 | Corrections Issued | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 8/18/2023 | Conditional Approval | DAVID FEILER |
| PLUMBING-Rough | 8/30/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 9/5/2023 | Partial Approval | JESUS PINEDA |
| Sewer | 9/5/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 9/20/2023 | Approved | JESUS PINEDA |
| Insulation | 9/20/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/8/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 11/16/2023 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 12/5/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 12/5/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 12/19/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/19/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/11/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 1/11/2024 | Approved | TEMISTOCLES CAAL |
| MERV13>=Rough | 1/11/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 1/16/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/25/2024 | Approved | JESUS PINEDA |
| Shower Pan | 1/25/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/31/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/7/2024 | Not Ready for Inspection | KENNETH NAGLE |
| Gas Test | 3/7/2024 | Approved | KENNETH NAGLE |
| PLUMBING-Final | 3/7/2024 | Approved | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | KENNETH NAGLE |
| Service/Power Release | 3/7/2024 | Approved | KENNETH NAGLE |
| Smoke Detectors | 3/7/2024 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 4/10/2024 | Approved | JESUS PINEDA |
| Green Building Final | 4/10/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 4/10/2024 | Approved | JESUS PINEDA |
| MERV13>=Final | 4/10/2024 | Corrections Issued | JESUS PINEDA |
| Final | 5/6/2024 | Corrections Issued | JESUS PINEDA |
| MERV13>=Final | 5/6/2024 | Approved | JESUS PINEDA |
| Final | 5/28/2024 | OK to Issue CofO | JESUS PINEDA |