13513 W BAYLISS ROAD 90049

Certificate Information: 13513 W BAYLISS ROAD 90049

Application / Permit
21014-30000-00154
Plan Check / Job No.
B21WL00166
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Conversion of attached garage to habitable space and addition to (E)xisiting 2 story SFD
Permit Issued
Issued on 11/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 FELIPE HERNANDEZ
Corrections Issued 2/9/2021 FELIPE HERNANDEZ
Quality Review Completed 2/19/2021 TARIK SAOUD
Applicant returned to address corrections 9/20/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 11/24/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 12/28/2021 FELIPE HERNANDEZ
Building Plans Picked Up 12/30/2021 APPLICANT
Applicant returned to address corrections 7/5/2022 FELIPE HERNANDEZ
Plan Check Approved 7/6/2022 FELIPE HERNANDEZ
Issued 11/18/2022 APPLICANT
CofO in Progress 7/30/2025 KEVIN SARGSYAN
Permit Finaled 8/4/2025 RICHARD STEINBACH
CofO Issued 8/4/2025 RICHARD STEINBACH
Permit Finaled 8/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/25/2021 TRACY TATE
BHO/Hillside ordinance Cleared 3/25/2021 TRACY TATE
BHO/Hillside ordinance Cleared 3/25/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 3/30/2021 TRACY TATE
BHO/Hillside ordinance Cleared 4/6/2021 TRACY TATE
BHO/Hillside ordinance Cleared 4/6/2021 TRACY TATE
Hydrant and Access approval Cleared 6/8/2021 ROBERT DUFF
Low Impact Development Cleared 8/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/10/2021 TRACY TATE
Sewer availability Cleared 11/10/2021 TRACY TATE
Grading Pre-Inspection Cleared 12/28/2021 FELIPE HERNANDEZ

Contact Information

Contractor Watson David Construction Inc; Lic. No.: 934184-B 4457 HAZELBROOK AVENUE      LONG BEACH, CA 90808
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/28/2022 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 2/8/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 2/8/2023 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/10/2023 Partial Approval KENNETH NAGLE
PLUMBING-Rough 2/14/2023 Partial Approval KEVIN SARGSYAN
Sewer 2/14/2023 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/20/2023 Approved KEVIN SARGSYAN
Deputy Reinf. Concrete 4/21/2023 No Access for Inspection KENNETH NAGLE
Pre-Inspection 5/9/2023 Partial Inspection KEVIN SARGSYAN
Deputy Steel/Welding 5/11/2023 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 5/24/2023 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval KEVIN SARGSYAN
Structural Steel Frame 5/25/2023 Partial Approval KEVIN SARGSYAN
Wood Frame 5/25/2023 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 6/23/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/28/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/28/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 8/11/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/11/2023 Approved KEVIN SARGSYAN
HVAC-Rough 8/22/2023 Corrections Issued KEVIN SARGSYAN
Shower Pan 8/23/2023 Approved KEVIN SARGSYAN
HVAC-Rough 8/30/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/5/2023 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 9/12/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/12/2023 Approved KEVIN SARGSYAN
Green Building Rough 9/12/2023 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 9/12/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/12/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 10/19/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/19/2023 Approved KEVIN SARGSYAN
Green Building Rough 10/19/2023 Approved KEVIN SARGSYAN
HVAC-Rough 10/19/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/19/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/19/2023 Approved KEVIN SARGSYAN
Wood Frame 10/19/2023 Approved KEVIN SARGSYAN
Insulation 10/23/2023 Approved KEVIN SARGSYAN
Drywall Nailing 11/1/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/17/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Final 4/17/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 4/17/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 5/15/2024 Approved KEVIN SARGSYAN
Final 5/15/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/15/2024 Approved KEVIN SARGSYAN
Green Building Final 5/15/2024 Approved KEVIN SARGSYAN
HVAC-Final 5/15/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 5/15/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 5/15/2024 Approved KEVIN SARGSYAN
Final 7/30/2025 OK to Issue CofO KEVIN SARGSYAN