5928 W 77TH PL 90045
Certificate Information: 5928 W 77TH PL 90045
- Application / Permit
- 21014-30000-00121
- Plan Check / Job No.
- B21WL00120
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior Remodel and 2-Story Addition to (E) 1-Story S.F.D
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | DAVID CASTILLO |
| Corrections Issued | 1/26/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/4/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/26/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/16/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/17/2021 | DAVID CASTILLO |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Applicant returned to address corrections | 1/25/2022 | DAVID CASTILLO |
| Plan Check Approved | 3/15/2022 | DAVID CASTILLO |
| Issued | 5/9/2022 | APPLICANT |
| CofO in Progress | 3/5/2024 | BOBBY KEY |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | TRACY TATE |
| Sewer availability | Cleared | 4/26/2021 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 7/28/2021 | BRIAN MILLER |
| Low Impact Development | Cleared | 9/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/12/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/18/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/21/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Conditional Approval | BOBBY KEY |
| Gas Test | 11/10/2022 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 11/10/2022 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 11/10/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/2/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/9/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 12/14/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/4/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 1/4/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/13/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 1/19/2023 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 1/19/2023 | Approved | BOBBY KEY |
| Insulation | 1/19/2023 | Partial Approval | BOBBY KEY |
| Insulation | 1/30/2023 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 2/3/2023 | Conditional Approval | BOBBY KEY |
| Drywall Nailing | 2/10/2023 | Conditional Approval | BOBBY KEY |
| Shower Pan | 2/23/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/13/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/22/2023 | Approved | BOBBY KEY |
| Final | 5/22/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/22/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/22/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/22/2023 | Approved | BOBBY KEY |
| HVAC-Final | 6/7/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 1/29/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/5/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 3/5/2024 | Approved | BOBBY KEY |
| Final | 3/5/2024 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 3/5/2024 | Approved | BOBBY KEY |
| Service/Power Release | 3/5/2024 | Approved | BOBBY KEY |