7651 W WILLOW GLEN ROAD 90046

Certificate Information: 7651 W WILLOW GLEN ROAD 90046

Application / Permit
21014-30000-00089
Plan Check / Job No.
B21WL00099
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior renovation including kitchen and bathrooms, raising ceilings, wall reconfiguring, window and door replacement, removal of (e) patio cover, and enclose portion of entry hall.
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 TARIK SAOUD
Corrections Issued 1/25/2021 TARIK SAOUD
Quality Review Completed 2/4/2021 CHIHARU SUZUKI
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 4/21/2021 TARIK SAOUD
Issued 6/15/2021 APPLICANT
CofO in Progress 9/3/2025 BRIAN SULLIVAN
Permit Finaled 9/4/2025 DEROLD HAUFF
CofO Issued 9/4/2025 DEROLD HAUFF
Permit Finaled 9/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/22/2021 BRIAN MILLER
Roof/Waste drainage to street Cleared 3/5/2021 RENZ SORIANO
Specific Plan Cleared 4/9/2021 OLGA AYALA
Eng Process Fee Ord 176,300 Cleared 4/14/2021 PAMELA TENEZA

Contact Information

Architect Gordon,, Brant Douglas; Lic. No.: C24403 12806 PACIFIC AVE 8      LOS ANGELES, CA 90066
Contractor Marco General Construction Inc; Lic. No.: 957126-B 4822 1/2 MCKINLEY AVE      LOS ANGELES, CA 90011
Engineer Chung,, Jun Sung; Lic. No.: S2766 15909 CARMENIA DR      WHITTIER, CA 90603

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/28/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 6/28/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 6/28/2021 Approved BRIAN SULLIVAN
Green Building Rough 6/28/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 6/28/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/28/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 7/8/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 7/8/2021 Approved RAUL BARAJAS
Green Building Rough 7/8/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 7/8/2021 Approved RAUL BARAJAS
PLUMBING-Rough 7/8/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 7/15/2021 Partial Approval RAUL BARAJAS
Green Building Rough 7/15/2021 Approved RAUL BARAJAS
Insulation 7/15/2021 Approved RAUL BARAJAS
Drywall Nailing 8/2/2021 Approved RAUL BARAJAS
Shower Pan 8/2/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 8/10/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 8/10/2021 Approved RAUL BARAJAS
Final 9/26/2022 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 9/26/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 9/26/2022 Approved BRIAN SULLIVAN