3641 S OCEAN VIEW AVE 90066
Certificate Information: 3641 S OCEAN VIEW AVE 90066
- Application / Permit
- 21014-30000-00085
- Plan Check / Job No.
- B21WL00091
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Dining room addition to (e) 1-story SFD. Kitchen and family room remodel. New family room.
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | RICHARD GARCIA |
| Corrections Issued | 1/17/2021 | RICHARD GARCIA |
| Plan Check Approved | 2/25/2021 | RICHARD GARCIA |
| No Progress | 3/31/2021 | RICHARD GARCIA |
| Plan Check Approved | 10/4/2021 | KHUONG TRUONG |
| Issued | 12/20/2021 | APPLICANT |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| CofO in Progress | 3/17/2023 | DAVID FEILER |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
| CofO Issued | 3/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 4/29/2021 | KIRK LINKLATER |
| Low Impact Development | Cleared | 9/21/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/28/2021 | NIKTA MOUSAVI |
Contact Information
| Architect | Chung,, Lincoln Kar-Wai; Lic. No.: C25222 | 2339 34TH STREET #38 SANTA MONICA, CA 90405 |
| Contractor | Nucon Group Inc; Lic. No.: 748689-B | 10336 MONTE MAR DRIVE LOS ANGELES, CA 90064 |
| Engineer | Lee,, Jaeyol; Lic. No.: C51639 | 430 S GARFIELD AVE SUITE 301 ALHAMBRA, CA 91801 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/22/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 5/11/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 5/11/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/11/2022 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deputy Wood Construction | 5/16/2022 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/17/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/17/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 5/17/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/20/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/20/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/20/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 5/20/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 5/20/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/20/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/20/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 5/25/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 7/18/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 8/15/2022 | Corrections Issued | JOHNNY MIRANDA |
| Final | 8/15/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/15/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 8/15/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 8/15/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 8/15/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 8/15/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 8/18/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/15/2023 | OK to Issue CofO | JOHNNY MIRANDA |