3847 S BERRYMAN AVE 90066

Certificate Information: 3847 S BERRYMAN AVE 90066

Application / Permit
21014-30000-00083
Plan Check / Job No.
B21WL00089
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ground floor addition to existing 1-story sfd.
Permit Issued
Issued on 4/23/2021
Issuing Office
Current Status
CofO Issued on 12/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 TARIK SAOUD
Corrections Issued 1/25/2021 TARIK SAOUD
Quality Review Completed 2/4/2021 CHIHARU SUZUKI
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 4/7/2021 TARIK SAOUD
Issued 4/23/2021 APPLICANT
CofO in Progress 12/20/2021 ENRIQUE MIRELES
CofO Issued 12/28/2021 DANIEL ORRANTE
Permit Finaled 12/28/2021 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 2/8/2021 FREDDY GARCIA
Sewer availability Cleared 2/18/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/19/2021 ANTHONY MAINEZ
Low Impact Development Cleared 3/23/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/30/2021 ANTHONY MAINEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Bems Construction; Lic. No.: 1014009-B 2930 E 5TH ST APT #8      LONG BEACH, CA 90814
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/2/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/3/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/23/2021 Partial Approval ENRIQUE MIRELES
Insulation 6/29/2021 Approved ENRIQUE MIRELES
Service/Power Release 7/1/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/30/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 8/30/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/30/2021 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 8/30/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 8/31/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/31/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/31/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 8/31/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 9/3/2021 Approved ENRIQUE MIRELES
Green Building Rough 9/3/2021 Approved ENRIQUE MIRELES
Wood Frame 9/3/2021 Approved ENRIQUE MIRELES
Insulation 9/8/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/8/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 9/15/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 9/15/2021 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 11/18/2021 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 11/18/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/9/2021 Approved ENRIQUE MIRELES
Final 12/9/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/9/2021 Approved ENRIQUE MIRELES
HVAC-Final 12/9/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/9/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/9/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/20/2021 Approved ENRIQUE MIRELES
Final 12/20/2021 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 12/20/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/20/2021 Approved ENRIQUE MIRELES