6550 W 84TH PL 90045

Certificate Information: 6550 W 84TH PL 90045

Application / Permit
21014-30000-00066
Plan Check / Job No.
B21WL00079
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st (505 sf) & 2nd (821 sf) story addition to (e) single-story SFD (1,077 sf)
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 REZA HAGHIGHAT
Corrections Issued 2/1/2021 REZA HAGHIGHAT
Quality Review Completed 2/10/2021 TARIK SAOUD
Plan Check Approved 5/12/2022 REZA HAGHIGHAT
Issued 8/19/2022 APPLICANT
Building Plans Picked Up 9/8/2022 APPLICANT
CofO in Progress 9/6/2024 TEMISTOCLES CAAL
Permit Finaled 9/7/2024 RICHARD STEINBACH
CofO Issued 9/7/2024 RICHARD STEINBACH
Permit Finaled 9/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 11/8/2021 LONDY ALVARADO
Eng Process Fee Ord 176,300 Cleared 11/15/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 11/15/2021 DINAH GARIN
Sewer availability Cleared 11/15/2021 DINAH GARIN

Contact Information

Architect Mackler,, Deborah Ellen; Lic. No.: C35957 334 SYCAMORE ROAD      SANTA MONICA, CA 90402
Contractor Owner-Builder       ,
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2022 Partial Inspection HERBERT GIRON
Pre-Inspection 1/30/2023 Partial Inspection HERBERT GIRON
Deputy Drilled-In Anchors 2/14/2023 Conditional Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 2/14/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 2/14/2023 Corrections Issued HERBERT GIRON
Deputy Drilled-In Anchors 4/14/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 4/14/2023 Approved HERBERT GIRON
Special/Order Compliance 4/14/2023 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 4/25/2023 Corrections Issued HERBERT GIRON
Green Building Rough 4/25/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 4/25/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 5/1/2023 Partial Approval HERBERT GIRON
Green Building Rough 5/1/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 5/1/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval HERBERT GIRON
Green Building Rough 5/3/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval HERBERT GIRON
Special/Order Compliance 5/12/2023 Corrections Issued HERBERT GIRON
Deputy Wood Construction 5/31/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 6/12/2023 Approved HERBERT GIRON
Insulation 6/27/2023 Partial Approval BOBBY KEY
HVAC-Rough 6/29/2023 Corrections Issued BOBBY KEY
Shower Pan 7/3/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/5/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 7/5/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 7/7/2023 Approved HERBERT GIRON
HVAC-Rough 8/18/2023 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 8/25/2023 Approved HERBERT GIRON
Green Building Rough 8/25/2023 Approved HERBERT GIRON
Special/Order Compliance 8/25/2023 Partial Inspection JESUS PINEDA
Verify Sprinkler Sign Off 8/25/2023 Approved HERBERT GIRON
Insulation 9/27/2023 Approved HERBERT GIRON
Drywall Nailing 10/6/2023 Approved KENNETH NAGLE
Pre-Inspection 12/4/2023 Partial Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 12/8/2023 Partial Approval RICHARD STEINBACH
Shower Pan 12/8/2023 Approved RICHARD STEINBACH
Interior/Exterior Lathing 12/12/2023 Approved TEMISTOCLES CAAL
HVAC-Final 4/11/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 4/19/2024 Corrections Issued TEMISTOCLES CAAL
Interior/Exterior Lathing 4/24/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 4/24/2024 Corrections Issued TEMISTOCLES CAAL
Gas Test 4/26/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 4/26/2024 Corrections Issued TEMISTOCLES CAAL
Interior/Exterior Lathing 5/6/2024 Approved TEMISTOCLES CAAL
Pre-Inspection 5/8/2024 Partial Inspection TEMISTOCLES CAAL
Special/Order Compliance 5/8/2024 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 5/22/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 5/30/2024 Approved TEMISTOCLES CAAL
Final 6/24/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 6/24/2024 Approved TEMISTOCLES CAAL
HVAC-Final 6/24/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 6/24/2024 Approved TEMISTOCLES CAAL
Final 9/5/2024 OK to Issue CofO TEMISTOCLES CAAL