5873 W ABERNATHY DR 90045
Certificate Information: 5873 W ABERNATHY DR 90045
- Application / Permit
- 21014-30000-00044
- Plan Check / Job No.
- B21WL00058
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st/2nd Story Addition and (N) Roof Deck
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | DAVID CASTILLO |
| Corrections Issued | 1/26/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/4/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/11/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/26/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 11/1/2022 | APPLICANT |
| Plan Check Approved | 12/2/2022 | DAVID CASTILLO |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 2/11/2026 | JESUS PINEDA |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/6/2021 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | NIKTA MOUSAVI |
| Low Impact Development | Cleared | 7/18/2022 | MARCO SANCHEZ |
| Sewer availability | Cleared | 11/1/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 11/3/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | M D H Builders / Design / Development; Lic. No.: 1067773-B | 6700 FALLBROOK AVE 100A WEST HILLS, CA 91307 |
| Engineer | Ayroso,, Ananias Maniquis; Lic. No.: S2413 | 12823 BERKHAMSTED ST CERRITOS, CA 90703 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2023 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/14/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 3/6/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/6/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 3/6/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/7/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 4/17/2023 | Approved | BOBBY KEY |
| HVAC-Final | 4/17/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/17/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/17/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/17/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 4/19/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/2/2023 | Approved | BOBBY KEY |
| Green Building Rough | 8/2/2023 | Approved | BOBBY KEY |
| Insulation | 8/2/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/2/2023 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 8/2/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 8/10/2023 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 8/15/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/16/2023 | Corrections Issued | RICHARD STEINBACH |
| Drywall Nailing | 8/16/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 8/16/2023 | Corrections Issued | RICHARD STEINBACH |
| Interior/Exterior Lathing | 8/22/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 4/2/2025 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 4/8/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 4/8/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 4/8/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 4/8/2025 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 4/8/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/11/2026 | Approved | JESUS PINEDA |
| Final | 2/11/2026 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 2/11/2026 | Approved | JESUS PINEDA |
| HVAC-Final | 2/11/2026 | Approved | JESUS PINEDA |
| PLUMBING-Final | 2/11/2026 | Approved | JESUS PINEDA |