137 N HOMEWOOD ROAD 90049
Certificate Information: 137 N HOMEWOOD ROAD 90049
- Application / Permit
- 21014-30000-00027
- Plan Check / Job No.
- B21WL00041
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Revise roof and add 200 sq ft to 2nd floor of (E) SFD
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | JASON JANGADA |
| Corrections Issued | 1/16/2021 | JASON JANGADA |
| Building Plans Picked Up | 1/20/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2021 | JASON JANGADA |
| Applicant returned to address corrections | 4/30/2021 | DAVID CASTILLO |
| Plan Check Approved | 5/9/2021 | DAVID CASTILLO |
| Issued | 5/17/2021 | APPLICANT |
| CofO in Progress | 8/4/2023 | KEVIN SARGSYAN |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
| CofO Issued | 8/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/19/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 2/22/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 4/23/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 5/9/2021 | JASON JANGADA |
Contact Information
| Contractor | Bloom Stephen Construction Inc; Lic. No.: 541421-B | 3934 CORAL PLACE CALABASAS, CA 91302 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/10/2021 | Conditional Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 6/18/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/10/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 9/8/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 9/14/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 9/14/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 9/23/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/23/2021 | Partial Approval | JUAN VALENZUELA |
| Insulation | 9/28/2021 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 9/28/2021 | Partial Inspection | RICHARD STEINBACH |
| Drywall Nailing | 10/4/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/1/2022 | Approved | MICHAEL PELHAM |
| Final | 3/1/2022 | Corrections Issued | MICHAEL PELHAM |
| Green Building Final | 3/1/2022 | Approved | MICHAEL PELHAM |
| HVAC-Final | 3/1/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Final | 3/1/2022 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 3/1/2022 | SGSOV Approved | MICHAEL PELHAM |
| Smoke Detectors | 3/1/2022 | Corrections Issued | MICHAEL PELHAM |
| Smoke Detectors | 3/3/2022 | Approved | JUAN VALENZUELA |
| Final | 8/4/2023 | OK to Issue CofO | KEVIN SARGSYAN |