200 N GUNSTON DR 90049

Certificate Information: 200 N GUNSTON DR 90049

Application / Permit
21014-20003-05261
Plan Check / Job No.
B22VN13709
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO REVISE FLOOR PLAN & ADD 28' X 38'4" RECREATION ROOM. MAJOR REMODEL & ADDITION TO SFD AND REMOVE ATTACHED GARAGE. NEW OVERALL BUILDING SIZE: 126'7"X185'6" NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 6/23/2023
Issuing Office
Valley
Current Status
Permit Finaled on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 MARVEL DELACRUZ
Corrections Issued 9/25/2022 MARVEL DELACRUZ
Quality Review Completed 9/28/2022 OMID HEDAYAT
Applicant returned to address corrections 1/24/2023 MARVEL DELACRUZ
Building Plans Picked Up 4/19/2023 APPLICANT
Applicant returned to address corrections 4/24/2023 MARVEL DELACRUZ
Applicant returned to address corrections 5/26/2023 MARVEL DELACRUZ
Plan Check Approved 6/23/2023 MARVEL DELACRUZ
Issued 6/23/2023 APPLICANT
Permit Finaled 7/12/2023 CARLOS MATAMOROS
Permit Finaled 7/13/2023 CARLOS MATAMOROS

Permit Application Clearance Information

Miscellaneous Cleared 10/4/2022 BRENNEN OBETO
Private street Cleared 10/4/2022 MIGUEL GAMBOA
BHO/Hillside ordinance Cleared 10/19/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/19/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/19/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/19/2022 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 10/19/2022 ANTHONY MAINEZ
Permit Cleared 10/19/2022 ANTHONY MAINEZ
Sewer availability Cleared 10/19/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 10/20/2022 ANTHONY MAINEZ
Low Impact Development Cleared 10/27/2022 ROGELIO CORTES
Distance to fire station Cleared 10/31/2022 GILBERT URREA
Hydrant and Access approval Cleared 10/31/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 11/4/2022 STEVEN JIN
GPI Written Notices Cleared 6/23/2023 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 6/23/2023 MARVEL DELACRUZ

Contact Information

Architect Stockton,, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/29/2023 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 6/29/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 7/11/2023 Corrections Issued CARLOS MATAMOROS
Green Building Rough 7/11/2023 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Rough 7/11/2023 Approved CARLOS MATAMOROS
Underground Mechanical 7/11/2023 Corrections Issued CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/11/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 7/12/2023 Approved CARLOS MATAMOROS
Drywall Nailing 7/12/2023 Approved CARLOS MATAMOROS
Final 7/12/2023 Permit Finaled CARLOS MATAMOROS
Footing/Foundation/Slab 7/12/2023 Approved CARLOS MATAMOROS
Green Building Final 7/12/2023 Approved CARLOS MATAMOROS
Green Building Rough 7/12/2023 Approved CARLOS MATAMOROS
MERV13>=Final 7/12/2023 Approved CARLOS MATAMOROS
MERV13>=Rough 7/12/2023 Approved CARLOS MATAMOROS
Smoke Detectors 7/12/2023 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/12/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/13/2023 Approved CARLOS MATAMOROS
Final 7/13/2023 Permit Finaled CARLOS MATAMOROS
Underground Mechanical 7/13/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 7/14/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 7/17/2023 Not Ready for Inspection CARLOS MATAMOROS