10861-10861 1/2 W NETTLETON ST 91352
Certificate Information: 10861-10861 1/2 W NETTLETON ST 91352
- Application / Permit
- 21014-20002-05381
- Plan Check / Job No.
- B23VN12493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPL TO 21014-20001-05381 TO CONVERT (E) SFD TO DUPLEX PER SB9 W/ 170 SQFT ADDITIONS. W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/24/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | PETER MOSESIAN |
| Corrections Issued | 9/30/2023 | PETER MOSESIAN |
| Quality Review Completed | 10/5/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 10/6/2023 | APPLICANT |
| Plan Check Approved | 10/24/2023 | PETER MOSESIAN |
| Issued | 10/24/2023 | APPLICANT |
| Permit Finaled-Status Void | 5/8/2025 | DAVID ANDERSON |
| Permit Finaled | 5/8/2025 | DAVID ANDERSON |
| Re-Activate Permit | 5/9/2025 | DAVID ANDERSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/5/2023 | COLIN LOREDO |
| Senate Bill 9 | Cleared | 10/19/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 10/19/2023 | NELSON RODRIGUEZ |
| ZI | Cleared | 10/19/2023 | NELSON RODRIGUEZ |
| Low Impact Development (LID) | Cleared | 10/20/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 10/20/2023 | JOHN LIN |
| Hydrant and Access approval | Cleared | 10/23/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/13/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| MERV13>=Rough | 12/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 12/13/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Approved | DAVID ANDERSON |
| Insulation | 12/18/2023 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 12/18/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 2/14/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 2/14/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/16/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/16/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/6/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 5/14/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 5/21/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/21/2024 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 5/21/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/2/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 7/2/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/9/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/10/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 1/31/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 1/31/2025 | Approved | DAVID ANDERSON |
| MERV13>=Final | 1/31/2025 | Approved | DAVID ANDERSON |
| Smoke Detectors | 1/31/2025 | Approved | DAVID ANDERSON |
| Final | 5/8/2025 | Permit Finaled | DAVID ANDERSON |
| Special/Order Compliance | 5/8/2025 | Approved | DAVID MATSON |