11939 1/4-1/2 W VALERIO ST 91605

Certificate Information: 11939 1/4-1/2 W VALERIO ST 91605

Application / Permit
21014-20001-05967
Plan Check / Job No.
B23VN06625
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 21014-20000-05967 TO REVISE TO 40' X 19'-6" ADDITON TO 20' X 20' (E) GARAGE TO CREATE (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g) and SB 897 and AB 2221 ALL WORK PER ENGINEERING AND TO RECAPTURE INVENTORY
Permit Issued
Issued on 2/13/2024
Issuing Office
Valley
Current Status
Permit Finaled on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/6/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/9/2023 OMID HEDAYAT
Building Plans Picked Up 6/12/2023 APPLICANT
Applicant returned to address corrections 12/26/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 2/13/2024 SEWADA ZADOORAN MILAGARDI
Issued 2/13/2024 APPLICANT
Permit Finaled 6/21/2024 JOSE AVILA

Permit Application Clearance Information

Address approval Cleared 8/16/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/16/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/16/2023 CARLOS AGUILERA
Sewer availability Cleared 8/16/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 12/15/2023 MELINEH AGHAKHABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/6/2024 Approved JOHN HAYES
Footing/Foundation/Slab 3/6/2024 Approved JOHN HAYES
METHANE-Barrier 3/6/2024 Approved JOHN HAYES
METHANE-Subgrade 3/6/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 3/18/2024 Partial Approval JOHN HAYES
Green Building Rough 3/18/2024 Not Ready for Inspection JOHN HAYES
METHANE-Rough 3/18/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/27/2024 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/27/2024 Not Ready for Inspection JOHN HAYES
METHANE-Rough 3/27/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 4/8/2024 Partial Approval JOHN HAYES
Green Building Rough 4/8/2024 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/7/2024 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 5/7/2024 Partial Approval JOHN HAYES
Interior/Exterior Lathing 5/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 5/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 5/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 5/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 6/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/11/2024 Not Ready for Inspection JOSE AVILA
Green Building Rough 6/11/2024 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 6/17/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/17/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/17/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 6/17/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ